This page has not been translated into Español. Visit the Español page for resources in that language.
EHP and Other Compliance
Appeal Brief
Desastre | 4020 |
Applicant | New York State Office of Parks, Recreation and Historic Preservation |
Appeal Type | Second |
PA ID# | 000-U0066-00 |
PW ID# | 9256 |
Date Signed | 2024-06-20T16:00:00 |
Summary Paragraph
From August 26 to September 5, 2011, Hurricane Irene caused damage in the state of New York. The Applicant requested $344,215.80 in funding for an HMP to replace destroyed headwalls and a dislodged culvert. FEMA prepared Project Worksheet (PW) 9256 to document the request. FEMA issued a request for information (RFI) but did not receive a response. FEMA found that all work was complete; it initiated an after-the-fact environmental and historic preservation (EHP) consultation as required by the National Historic Preservation Act. FEMA determined the project likely necessitated archaeological monitoring and proposed a geotechnical investigation. FEMA issued another RFI. The Applicant responded, claiming it never received FEMA’s request for an investigation and recommended moving forward with obligating the project by reevaluating the need for the investigation or a memorandum of agreement. FEMA denied the project stating it was unable to verify the level of disturbance during project construction. It also found that the Applicant did not provide the necessary permitting documentation required under the CWA. The Applicant appealed, arguing the investigations required by FEMA were not warranted and that FEMA did not follow its own procedures by not approving or obligating the project. The FEMA Region 2 Regional Administrator denied the appeal finding the Applicant did not afford FEMA the opportunity to complete its EHP review prior to completing the work, nor did it provide the necessary permitting documentation required under the CWA. The Applicant submitted a second appeal reiterating its first appeal arguments.
Authorities
- Stafford Act § 406(a)(1)(A), 42 U.S.C § 5172(a)(1)(A); 33 U.S.C. §§ 1311, 1344(a); National Historic Preservation Act § 106, 16 U.S.C § 470f.
- 36 C.F.R. §§ 800.1(a), (c), 800.2(c), 800.4, 800.6(c)(3), 800.14(b), 800.14(b)(1); 44 C.F.R. § 206.206(a).
- PA Guide, at 127, 130-132.
- Hutchinson County, FEMA-4469-DR-SD at 2.
Headnotes
- FEMA must review each PA project to ensure the work complies with applicable Federal EHP laws, including section 106 of the NHPA, and their implementing regulations.
- The Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work and FEMA determined an after-the-fact consultation to be infeasible.
- The Applicant must obtain a permit in any situation where dredging or filling is a component of the project.
- The Applicant has not provided the required applications or permits issued by the U.S. Army Corps of Engineers (USACE) and New York State Department of Environmental Conservation (NYSDEC) that demonstrate compliance with the CWA.
Conclusion
The Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work. Additionally, the Applicant has not demonstrated it complied with federal and state EHP laws. Therefore, the appeal is denied.
Appeal Letter
SENT VIA EMAIL
Rayana Gonzales
Deputy Commissioner for Disaster Recovery Programs, Alternate Governor’s Authorized Representative
New York State Division of Homeland Security and Emergency Services
1220 Washington Avenue, Building 7A, 4th Floor
Albany, New York 12242
Christopher S. Holmes
Director of Emergency Management
New York State Office of Parks, Recreation and Historic Preservation
625 Broadway
Albany, New York 12238
Re: Second Appeal – New York State Office of Parks, Recreation and Historic Preservation,
PA ID:000-U0066-00, FEMA-4020-DR-NY, Project Worksheet (PW) 9256, EHP and Other Compliance
Dear Rayana Gonzales and Christopher S. Holmes:
This is in response to the New York State Division of Homeland Security and Emergency Services (Recipient) letter dated March 19, 2024, which transmitted the referenced second appeal on behalf of the New York State Office of Parks, Recreation and Historic Preservation (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of funding in the amount of $344,215.80 plus archeological testing costs for its Hazard Mitigation Proposal to replace the culvert along the Lower Awosting Carriageway.
As explained in the enclosed analysis, I have determined the Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work. Additionally, the Applicant has not demonstrated it complied with federal and state EHP laws. Therefore, this appeal is denied.
This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.
Sincerely,
/S/
Robert Pesapane
Division Director
Public Assistance Division
Enclosure
cc: David Warrington
Regional Administrator
FEMA Region 2
Appeal Analysis
Background
From August 26 through September 5, 2011, Hurricane Irene caused damage throughout the state of New York.[1] The New York State Office of Parks, Recreation and Historic Preservation (Applicant) stated that heavy rains and rushing water washed away the embankment along the Lower Awosting Carriageway (Facility) at Minnewaska State Park. Specifically, the Applicant noted that flooding eroded the hillside embankment, destroyed two headwalls, and dislodged 100 linear feet of reinforced concrete pipe culvert. The Applicant requested $344,215.80 in Public Assistance (PA) funding for repairs and hazard mitigation to the Facility.
The Facility is part of a network of trails and roads built between 1870 and 1929 in Ulster County and is an eligible resource for listing in the National Register of Historic Places.[2] The Applicant’s requested scope of work (SOW) included a Hazard Mitigation Proposal (HMP) to replace the concrete pipe with a larger precast concrete box culvert, lower the road profile, and move the crossing to facilitate a low water crossing. On March 10, 2015, FEMA prepared Project Worksheet (PW) 9256 to document the requested costs.[3] FEMA advised that the project would be subject to all FEMA-required reviews, including Environmental and Historic Preservation (EHP) reviews, which may affect final funding for this project.
On April 8, 2016, FEMA issued a Request for Information (RFI), seeking technical studies, specifications, clarification of the proposed culvert, and U.S. Army Corps of Engineers (USACE) and New York State Department of Environmental Conservation (NYSDEC) permits. FEMA did not receive a response to the RFI, and therefore removed $35,541.00 for HMP costs from the PW. Subsequently, FEMA initiated an EHP review and determined the Applicant completed work on May 3, 2012, before the Agency could consult with necessary officials and interested parties as required under section 106 of the National Historic Preservation Act (NHPA).[4]
FEMA determined that because the project was completed prior to FEMA’s review and approval, there was no way to accurately determine the level of disturbance that occurred at the Facility. FEMA initiated an after-the-fact Section 106 consultation on March 27, 2017, with the New York State Historic Preservation Office (SHPO) and the New York State Division of Homeland Security and Emergency Services (Recipient).[5] FEMA determined the project’s SOW likely necessitated archaeological monitoring and proposed a geotechnical investigation in an effort to determine the level of disturbance from previous work and natural erosion on the Facility as well as a clearer picture of whether natural soils were impacted during construction.[6]
On April 11, 2022, FEMA issued an RFI requesting the status of the geotechnical investigation and USACE and NYSDEC permits and/or documentation demonstrating compliance with the Clean Water Act (CWA). The Applicant responded on May 9, 2022, stating that FEMA omitted important information when it submitted the request for section 106 consultation on March 27, 2017 such as: (1) the soil for the Facility had been replaced in 2009 after a previous disaster, so all the work was being performed on fill; (2) the declared incident had eroded 3,000 cubic yards of soil; (3) the project included more than the replacement of a culvert; and (4) the extent or location of the “new ground disturbance.” Additionally, the Applicant claimed it never received FEMA’s request to perform a geotechnical investigation.[7] The Applicant recommended moving forward with obligating the project by either a re-evaluation of the need for an archaeological investigation or a memorandum of agreement (MOA) laying out the archeological procedures to be followed.[8]
On September 26, 2022, FEMA issued a determination letter denying all requested funding.[9] FEMA explained it could not determine the effect for NHPA without fully understanding the degree of ground disturbance at the Facility and could not execute an MOA since there was not enough information to make a determination of adverse effect. Additionally, FEMA found the Applicant had not demonstrated CWA compliance by providing permits or a statement of compliance with a Nationwide Permit (NWP).
First Appeal
In a letter dated November 28, 2022, the Applicant submitted a first appeal, requesting $344,215.80 for the repair work and the HMP; it noted that costs may increase further depending on the archaeological testing mandated by FEMA. The Applicant argued that the Advisory Council on Historic Preservation’s (ACHP) regulations allowed for concluding a review with a Programmatic Agreement where effects could not be determined prior to the project’s approval. The Applicant claimed that the SHPO offered to draft such an agreement and reopen the consultation process based on its understanding that there was no potential for intact archaeological resources in the area of repair and that the investigations required by FEMA were not warranted. Additionally, the Applicant argued FEMA did not follow its own procedures in that it did not approve or obligate a PW for the project as required by Title 44 of the Code of Federal Regulations (C.F.R.) §§ 206.202(a) and (d)(1)(i). On January 26, 2023, the Recipient submitted the Applicant’s appeal along with a letter in support of the Applicant’s request.
On November 20, 2023, the FEMA Region 2 Regional Administrator denied the appeal. FEMA found that the Applicant did not afford the Agency the opportunity to complete an EHP review prior to starting the work. Regarding the Applicant’s proposal to re-start the consultation process, FEMA noted that the Tribal Historic Preservation Offices (THPOs) decided not to continue with the process, and that consultation would be infeasible without their participation. Further, FEMA found the Applicant did not provide the necessary permitting documentation required to show compliance with the CWA.
Second Appeal
In a letter dated January 19, 2024, the Applicant submitted a second appeal, reiterating its previously raised arguments. The Applicant clarifies its contention that FEMA failed to follow its own procedures at 44 C.F.R. § 206.201(d)(1) because FEMA did not draft a PW that included the costs of the EHP requirement to perform a geotechnical investigation. The Applicant also provides documentation such as email correspondence, programmatic agreements, and MOAs to support its appeal. The Applicant claims that the emails document its interactions with USACE regarding permitting issues for the project and that USACE stated it did not need to be notified about the construction work because activities authorized by an NWP (specifically, NWP 3) do not require notification. On March 19, 2024, the Recipient transmitted the second appeal along with its letter in support of the Applicant. The Recipient claims that FEMA’s determination that consultation is infeasible without the THPO’s participation conflicts with the ACHP’s NHPA regulations,[10] represents a new interpretation of the feasibility language in its Statewide Programmatic Agreement without input from other signatories, and constitutes a procedurally improper change in position from 2017 when FEMA was willing to go forward with consultation despite tribal concerns.
Discussion
FEMA may provide PA funding for the repair, restoration, reconstruction, or replacement of facilities damaged or destroyed by a major disaster.[11] FEMA must review each PA project to ensure the work complies with applicable Federal EHP laws, including section 106 of the NHPA and section 404 of the CWA, and their implementing regulations.[12] Reviews for compliance with EHP laws must be completed before FEMA approves funding and before work is started since the review may identify steps to be taken or conditions to be met before the project can be implemented.[13] Section 106 of the NHPA requires FEMA to consider the effects a project will have on historic properties and provide the ACHP the opportunity to comment on the effects of the project.[14] Also, section 106 of the NHPA and its implementing regulations at Title 36 of the C.F.R., Part 800, mandate that FEMA identify historic properties and cultural resources that may be affected by FEMA-funded activities, evaluate the impact of proposed work on the properties, and consult with the SHPO/THPO and other interested parties prior to the approval of any federal funds for the project.[15] In some cases, FEMA may establish a programmatic agreement with the ACHP, SHPO, and/or the THPO at the beginning of the disaster recovery process to address projects potentially falling within the scope of the NHPA.[16] Some uses for programmatic agreements are when effects on historic properties are similar and repetitive; when effects on historic properties cannot be fully determined prior to approval of an undertaking; and when nonfederal parties are delegated major decision-making responsibilities.[17]
Here, the Applicant completed the work before FEMA could conduct an EHP review. The New York Statewide Programmatic Agreement (Agreement) executed by FEMA, the State, and one or more Tribes, provided that where FEMA determined an applicant had initiated an undertaking without willful intent to avoid the requirements of the Agreement or section 106 of the NHPA, FEMA would determine if the undertaking would have required section 106 review.[18] If so, FEMA was required to coordinate with the SHPO and participating Tribal Nations to determine if consultation was feasible.[19] If after coordination with the SHPO, and appropriate Tribes, FEMA determined that a review was infeasible, FEMA would document the outcome and make a funding eligibility decision.[20] In this project, FEMA determined a section 106 review would have been required to fund the project and followed procedures established in Section III(D)(3) of the Agreement to initiate an after-the-fact consultation for a section 106 review. After subsequently learning that the Applicant had not performed a geotechnical investigation[21] of the area more than five years after FEMA proposed doing so to assess the potential impact to historic properties, and after considering further input and concerns from tribal representatives, FEMA determined the after-the-fact consultation would be infeasible.
Additionally, the Applicant did not provide the USACE and NYSDEC permits and/or documentation demonstrating CWA compliance that FEMA requested. Although the Applicant cites to correspondence with USACE pertaining to NWP 3 notification requirements, the correspondence does not confirm the Applicant met the conditions of the NWP and the Applicant has not explained how it applies to the work at issue here. Therefore, the Applicant has not demonstrated it complied with federal and state EHP laws.
Conclusion
The Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work. Additionally, the Applicant has not demonstrated it complied with federal and state EHP laws. Therefore, the appeal is denied.
[1] The President declared a major disaster, FEMA-4020-DR-NY, on August 31, 2011.
[2] See Letter from Env’t and Hist. Pres. Supervisor, FEMA Region 2, to Deputy State Hist. Pres. Officer, Div. for Hist. Pres., N.Y. State Office of Parks, Recreation & Hist. Pres., at 2-3 (Mar. 27, 2017) [hereinafter After-the-fact Consultation Letter].
[3] FEMA did not obligate costs.
[4] National Historic Preservation Act § 106, Title 16, United States Code (U.S.C.) § 470f (2006) (Section 106 is now codified at 54 U.S.C. § 306108 (2018)). Section 106 requires all federal agencies to consider the effects of their undertakings on historic properties. This is “triggered” by federal involvement, not by the presence of historic properties.
[5] After-the-fact Consultation Letter.
[6] After-the-fact Consultation Letter, at 3; Email from EHP Supervisor, FEMA Region 2, to N.Y. State Div. of Homeland Sec. and Emergency Servs., (May 18, 2017, 16:04 EST) [hereinafter Email from EHP].
[7] In contra: Email from Deputy Chief of Recovery – Administrative Support Unit, N.Y. State Div. of Homeland Sec. and Emergency Servs. to EHP Supervisor, FEMA Region 2 (July 7, 2017, 14:47 EST) (stating, in response to FEMA’s follow up on Email from EHP, that “We reached out to Parks again today and will forward any information we receive as soon as we get it.”).
[8] See Letter from Dir. of Emergency Mgmt., Office of Parks, Recreation and Hist. Pres., to Pub. Assistance and Env’t and Hist. Pres., FEMA Region 2, at 1-2 (May 9, 2022).
[9] The Applicant received FEMA’s determination letter on September 30, 2022.
[10] See Title 36 of the Code of Federal Regulations (C.F.R.) § 800.6(c)(3) (2011) (“The agency official may invite all consulting parties to concur in the memorandum of agreement. The signatories may agree to invite others to concur. The refusal of any party invited to concur in the memorandum of agreement does not invalidate the memorandum of agreement.”).
[11] Robert T. Stafford Disaster Relief and Emergency Assistance Act § 406(a)(1)(A), Title 42, U.S.C § 5172(a)(1)(A) (2006).
[12] See Public Assistance Guide, FEMA 322, at 127 (June 2007) [hereinafter PA Guide]; FEMA Second Appeal Analysis, Hutchinson Cnty., FEMA-4469-DR-SD, at 2 (June 29, 2022) (applying a policy that was issued subsequent to this disaster, but which contained substantially similar language to the policy provision applicable to this appeal).
[13] PA Guide, at 128.
[14] National Historic Preservation Act § 106, Title 16, U.S.C. § 470f; 36 C.F.R. § 800.1(a); PA Guide, at 130-131.
[15] National Historic Preservation Act § 106, Title 16, U.S.C. § 470f; 36 C.F.R. §§ 800.1(c), 800.2(c), 800.4; PA Guide, at 131.
[16] 36 C.F.R. § 800.14(b); PA Guide, at 131.
[17] 36 C.F.R. § 800.14(b)(1).
[18] See New York Statewide Programmatic Agreement, at 26 (May 10, 2013) [hereinafter Programmatic Agreement].
[19] Id.
[20] Id.
[21] FEMA sent an Email from EHP proposing a geotechnical investigation of the project area. Per the Programmatic Agreement at 12 “DHSES shall ensure that its subgrantees understand conditions and potential requirements that may be placed upon Undertakings as a result of Section 106 consultation and the provisions of this Agreement and that failure to comply with the terms of this Agreement and any project-specific conditions could jeopardize FEMA funding.”