Result of Declared Incident

Appeal Brief Appeal Letter Appeal Analysis

Appeal Brief

Disaster4594
ApplicantMemphis Light, Gas, and Water
Appeal TypeSecond
PA ID#157-0464A-00
PW ID#GMP 186743
Date Signed2023-12-26T17:00:00

Summary Paragraph

From February 11 to 19, 2021, a winter storm impacted Memphis, Tennessee, the location of an underground parking garage (Facility) owned by Memphis Light, Gas, and Water (Applicant). The Applicant claimed that snow and ice accumulation on different areas of the Facility’s roof, located under a landscaped grassy area, caused structural cracking and water damage from freezing pipes. FEMA prepared Grants Manager Project 186743 to capture claimed damage (structural cracking of the roof) and Applicant-estimated repair costs of $1,994,940.00. FEMA reviewed several documents including a site inspection report that described measures taken to prevent hairline cracks from propagating and water infiltration, and an insurance denial letter based on a damages’ evaluation. After reviewing the documentation, FEMA determined the work was ineligible, as the Applicant had not demonstrated the repair work was required as a result of the declared incident. The Applicant appealed, requesting $3,727,962.00 for repair costs. The increased costs were due to additional claimed structural damages and repair work. FEMA denied the appeal as the administrative record did not demonstrate that the claimed damage directly resulted from the incident and was not the result of pre-existing causes such as deterioration or deferred maintenance. The Applicant’s second appeal reiterates first appeal arguments and includes a comprehensive report of the Applicant’s failure investigation, which states the disaster caused an increase in load that contributed to the failure. 

Authorities and Second Appeals

  • Stafford Act § 406(a)(1).
  • 44 C.F.R. § 206.223(a)(1).
  • PAPPG, at 51-52, 63-64.

Headnotes

  • To be eligible for PA funding, an item of work must be required as a result of the major disaster, and the applicant must demonstrate that the damage was directly caused by the incident. 
    • The Facility was functioning before the disaster and damages following the disaster rendered approximately 25 percent of the Facility non-functional. The Applicant has demonstrated the disaster damaged the Facility and the claimed repairs are required as a result of the declared incident.
      Conclusion

FEMA finds the Applicant has demonstrated that work to restore the Facility is required as a result of the declared incident. Therefore, the appeal is granted. 


 

Appeal Letter

SENT VIA EMAIL

Patrick Sheehan                                                            Sharon Spence            

Director                                                                           Supervisor, Property and Accounting

Tennessee Emergency Management Agency           Memphis Light, Gas, and Water

3041 Sidco Drive                                                             220 South Main Street            

Nashville, Tennessee 37204                                       Memphis, Tennessee 38103

 

Re:  Second Appeal – Memphis Light, Gas, and Water, PA ID: 157-0464A-00, FEMA-4594-DR-TN, Grants Manager Project 186743, Result of Declared Incident

 

Dear Patrick Sheehan and Sharon Spence:

This is in response to the Tennessee Emergency Management Agency’s (Recipient) letter dated July 12, 2023, which transmitted the referenced second appeal on behalf of Memphis Light, Gas, and Water (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of funding in the amount of $3,727,962.00 for repairs to a parking garage (Facility).

As explained in the enclosed analysis, I have determined the Applicant has demonstrated that work to restore the Facility is required as a result of the declared incident. Therefore, the appeal is granted. By copy of this letter, I am requesting the Regional Administrator to take appropriate action to implement this determination, including reviewing this project’s cost eligibility.

This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.

 

                                                                                                Sincerely, 

                                                                                                       /S/

                                                                                               Robert Pesapane

                                                                                               Division Director

                                                                                               Public Assistance Division

 

Enclosure

cc:  Robert D. Samaan 

Regional Administrator 

FEMA Region 4

Appeal Analysis

Background

From February 11 to 19, 2021, a winter storm impacted Memphis, Tennessee, the location of an underground parking garage (Facility), owned by Memphis Light, Gas, and Water (Applicant). The Applicant claimed that snow and ice accumulation on different areas of the Facility’s roof, located under a landscaped grassy area, caused structural cracking and water damage from freezing pipes. FEMA prepared Grants Manager Project 186743 to capture the claimed damage (e.g., structural cracking of the roof) and Applicant-estimated repair costs of $1,994,940.00 to replace portions of the Facility’s roof. FEMA issued a Determination Memorandum (DM), finding the claimed repair work ineligible because FEMA could not validate the existence of disaster-related damage as opposed to damage resulting from the Facility’s age, deterioration, or deferred maintenance. In making its determination, FEMA noted it reviewed documents provided by the Applicant, including: (1) a building maintenance email[1] that described predisaster measures taken to prevent hairline cracks from propagating and water infiltration; (2) FEMA’s site inspection report (SIR);[2] and (3) an insurance denial letter[3] that found that cracking had been happening over time and was not related to the disaster (based on a damages’ evaluation conducted by an insurer-contracted structural engineer). 

First Appeal 

The Applicant submitted its first appeal on March 28, 2022, requesting $3,727,962.00 for repair costs.[4] In addition to previously claimed structural cracking of the roof, the Applicant’s structural engineer noted flexural and shear failure at the beam/column interface of one location and additional cracking at two other locations. The engineer stated approximately 25 percent of the Facility was unusable for parking.[5] In its appeal letter, the Applicant explained that the unusually heavy snowfall deposited by the disaster, accumulating up to 10 inches, led to the sudden failure of the Facility. In support of its claim, the Applicant provided predisaster insurance company risk evaluation reports from 2019 and 2020 that showed no structural damages to the Facility. The Applicant also provided post-disaster photographs, a repair and improvement history of the Facility dating to 1978, and other relevant documentation. In addition, the Applicant stated the Facility was originally constructed in compliance with building codes in place at that time. The Tennessee Emergency Management Agency (Recipient) forwarded the appeal with its support by letter dated May 10, 2022.

FEMA issued a request for information (RFI) on August 24, 2022, seeking information demonstrating the condition of the Facility immediately prior to the disaster, other factors that may have contributed to overextension of the Facility’s weight capacity, and any post-disaster assessments from firms that specialize in forensic engineering and/or failure analysis that considered the cause of the damage. 

The Applicant responded on September 22, 2022 with several exhibits. These included: (1) Climatological Data which showed that temperatures dropped from a low of 30 degrees on February 10, 2021 to a low of one degree on February 16, 2021 and 10 inches of snow accumulation; (2) the Proof of Loss from the Applicant’s engineer; and (3) a Garage Damage Review from the structural engineer for the company that oversaw Facility repairs. The Applicant included statements from its in-house structural engineer finding that the disaster caused the damage, the Facility had no sign of long-term water intrusion that would compromise its structural integrity, and the existing waterproofing membrane accompanied by a topping slab and an impermeable layer of clay performed exceptionally well. The structural engineer further noted the Facility was constructed in accordance with codes in effect at the time of construction and there was no documented indication of distress at damaged location sites prior to the disaster. 

FEMA’s Region 4 Regional Administrator denied the appeal on April 27, 2023, finding the Applicant had not demonstrated the Facility was damaged as a direct result of the disaster. FEMA stated the 2019 insurance risk evaluation report did not address the Facility’s physical condition and did not verify its predisaster condition. FEMA noted the Applicant’s engineer’s Proof of Loss implied that age-related wear and tear likely contributed to the Facility’s failure.[6] FEMA pointed to predisaster maintenance records that indicated frequent incidents of water leakage and noted that such occurrences, coupled with repeated freeze-thaw cycles, could potentially result in the deterioration and failure of concrete. FEMA found the Applicant did not provide any structural analysis demonstrating how the snow and ice accumulation could have resulted in the Facility’s failure if it were functioning at optimal capacity.

Second Appeal

In a second appeal dated June 26, 2023, the Applicant reiterates first appeal arguments.[7] The Applicant notes it hired an expert who conducted a comprehensive failure investigation and addressed questions related to the Facility’s physical condition. The report concluded that the disaster caused an increase in load, contributing to the structural failure of the Facility.[8] The Recipient supports the Applicant with its transmittal dated July 12, 2023.

 

Discussion

FEMA may provide Public Assistance (PA) funding to restore eligible facilities damaged or destroyed by major disasters based on pre-disaster design and function and in conformity with current applicable codes, specifications, and standards.[9]To be eligible for PA funding, an item of work must be required as a result of the declared incident, and the applicant must demonstrate that the damage was directly caused by the incident.[10] FEMA does not provide funding for repair of damage caused by deterioration or deferred maintenance.[11] When necessary to validate damage, FEMA may require the applicant to provide documentation supporting the predisaster condition of the facility (e.g., facility maintenance records, inspection/safety reports).[12] If a facility was functioning prior to the disaster and the disaster caused damage that rendered the facility non-functional, the facility may be eligible provided the predisaster condition was not a significant contributing factor in the cause of failure.[13] The applicant is responsible for providing documentation to support its claim as eligible.[14]

In its second appeal, the Applicant provided an engineer’s report verifying that the Facility’s roof and structural damages were directly caused by the disaster’s freezing temperatures, heavy rains, snow, and ice. In addition, theClimatological Data document shows the Facility received 10 inches of new snow between February 10-17, 2021, and experienced a temperature drop from a low of 30 degrees on February 10, to a low of 1 degree on February 16, 2021. Furthermore, the Applicant’s comprehensive failure investigation, conducted by a licensed professional engineer, concluded the disaster caused an increase in load weight that substantially contributed to the failure of the Facility’s roof structure. This report provides a more detailed forensic analysis of the Facility’s failure compared to the prior reports and documentation submitted. 

Cited reports indicate that the Facility design likely contributed to the damages. For example, the SIR noted very little shear reinforcing was required when the Facility was built,[15] and the ABS Report stated that due to the original design, the Facility had a low safety factor against failure.[16] FEMA considered that the Facility was constructed in accordance with codes in effect at the time of construction, and that updated codes put in place after construction may have prevented the damages caused by the disaster, and has determined these are not evidence of deterioration, deferred maintenance, failure to prevent damage, or negligence.

Reviewing the documents provided on second appeal, in addition to all the documents cited in the DM, insurance risk evaluations, the Applicant’s first and second appeal letters, and the RFI response supports the Applicant’s assertion that the snow load from the disaster caused of the failure. The insurance and engineering documentation shows the Facility showed wear and tear, but was functioning prior to the disaster, in particular where the reports note the Facility had no sign of long-term water intrusion that would compromise its structural integrity, and the existing waterproofing membrane accompanied by a topping slab and an impermeable layer of clay performed exceptionally well. Here, the disaster caused damage that rendered one-quarter of the Facility non-functional and the Applicant has demonstrated the predisaster condition was not a significant contributing factor in the cause of failure. Consequently, work to restore the Facility is required as a result of the declared incident.

 

Conclusion

The Applicant has demonstrated that work to restore the Facility is required as a result of the declared incident. Therefore, the appeal is granted.[17]


 

[1] Email from Supervisor Prop. Acct., Memphis Light, Gas, and Water (MLGW), to Program Delivery Manager, FEMA (Aug. 12, 2021, 1627 CDT).

[2] Site Inspection Report, FEMA-4594-DR-TN MLGW, WO72152-D462750, Project 186743, at 4 (Sept. 20, 2021).

[3] Letter from Senior Adjuster, Factory Mutual Insurance Company, to Manager, Insurance and Pensions, MLGW (Sept. 27, 2021). The denial letter cited Solis Parker & Associates, Inc., FM Global – Memphis Light, Gas & Water Division – Parking Garage Damages Evaluation (Sept. 17, 2021). The structural engineer researched historical weather records for February 16-17, 2021, and found no significant snow accumulation and a temperature drop of 5 degrees that lasted less than 24 hours.

[4] The Applicant’s structural engineer noted the estimated cost to repair/replace was much greater than originally estimated. A cost sheet submitted on first appeal listed emergency shoring, contracted emergency work, removal and installation of utility elements, and construction repair costs. Amended and Supplemental Proof of Loss/Claim (Jan. 27, 2022) [hereinafter Proof of Loss].

[5] The Applicant’s structural engineer detailed that the Applicant protected the Facility from further damage by installing various measures to prevent further collapse of the Facility and avoid additional damages. Id.

[6] Proof of Loss (stating that the structural failure was due to “twin culprits … weather and age of the building”).

[7] Letter from Attorney, BMJRG, to Dir., Tenn. Emergency Mgmt. Agency (June 26, 2023). The Applicant also includes documents related to an ongoing federal litigation against its insurance company, in which the Applicant challenges the insurance company’s assertion that the disaster was not the cause of the damage.

[8] Applied Bldg. Sciences, Inc. (ABS), ABS Project No. 900.22049 (Jan. 30, 2023) [hereinafter ABS Report].

[9] Robert T. Stafford Disaster Relief and Emergency Assistance Act § 406(a)(1), Title 42, United States Code 

§ 5172(a)(1) (2018); Stafford Act § 406(e), 42 U.S.C. § 5172(e); Title 44 Code of Federal Regulations § 206.226(d); Public Assistance Program and Policy Guide, FP 104-009-2, at 145 (June 1, 2020) [hereinafter PAPPG]. 

[10] 44 C.F.R. § 206.223(a)(1) (2020); PAPPG, at 51-52.

[11] PAPPG, at 52.

[12] Id.

[13] Id.

[14] Id. at 63-64.

[15] SIR, at 4.

[16] ABS Report, at 17.

[17] FEMA directs the Region 4 Regional Administrator to review this project’s cost eligibility. This may include reviewing the Applicant’s compliance with procurement requirements and/or performing a cost reasonableness analysis. FEMA may also perform an insurance review which may result in a deduction of costs based on coverage in the insurance policy as well as any anticipated or actual insurance proceeds recovered by the Applicant in any manner. The Applicant’s appeal rights concerning a future determination are reserved.

Last updated