The Department of Homeland Security (DHS) Notice of Funding Opportunity (NOFO) Fiscal Year 2023 Emergency Operations Center Grant Program

Release Date:
March 1, 2023

Download a PDF copy of this webpage.

Effective April 4, 2022, the Federal Government transitioned from using the Data Universal Numbering System or DUNS number, to a new, non-proprietary identifier known as a Unique Entity Identifier or UEI. For entities that have an active registration in the System for Award Management (SAM) prior to this date, the UEI has automatically been assigned and no action is necessary. For all entities filing a new registration in SAM.gov on or after April 4, 2022, the UEI will be assigned to that entity as part of the SAM.gov registration process.

UEI registration information is available on GSA.gov at Unique Entity Identifier Update | GSA.

Visit Grants.gov for registration information. Detailed information regarding UEI and SAM is also provided in Section D of this funding notice.

Table of Contents

A.    Program Description

  1. Issued By
  2. Assistance Listings Number
  3. Assistance Listings Title
  4. Funding Opportunity Title
  5. Funding Opportunity Number
  6. Authorizing Authority for Program
  7. Appropriation Authority for Program
  8. Announcement Type
  9. Program Category
  10. Program Overview, Objectives and Priorities
  11. Performance Measures

B.    Federal Award Information

  1. Available Funding: $89,140,285
  2. Period of Performance: 36 months   
  3. Projected Period of Performance Start Date(s): No later than 06/01/2023
  4. Projected Period of Performance End Date(s): No later than 05/31/2026
  5. Funding Instrument Type: Grant

C.    Eligibility Information

  1. Eligible Applicants
  2. Applicant Eligibility Criteria
  3. Other Eligibility Criteria
  4. Cost Share or Match

D.    Application and Submission Information

  1. Key Dates and Times
  2. Agreeing to Terms and Conditions of the Award
  3. Address to Request Application Package
  4. Requirements: Obtain a Unique Entity Identifier (UEI) and Register in the System for Award Management (SAM)
  5. Steps Required to Obtain a Unique Entity Identifier, Register in the System for Award Management (SAM), and Submit an Application
  6. Electronic Delivery
  7. How to Register to Apply through Grants.gov
  8. How to Submit an Initial Application to FEMA via Grants.gov
  9. Submitting the Final Application in ND Grants
  10. Timely Receipt Requirements and Proof of Timely Submission
  11. Content and Form of Application Submission
  12. Intergovernmental Review
  13. Funding Restrictions and Allowable Cost

E.    Application Review Information

  1. Application Evaluation Criteria
  2. Review and Selection Process

F.    Federal Award Administration Information

  1. Notice of Award
  2. Pass-Through Requirements
  3. Administrative and National Policy Requirements
  4. Reporting
  5. Monitoring and Oversight 

G.    DHS Awarding Agency Contact Information

  1. Contact and Resource Information
  2. Systems Information

H.    Additional Information

  1. Termination Provisions
  2. Program Evaluation
  3. Period of Performance Extensions
  4. Disability Integration
  5. Conflicts of Interest in the Administration of Federal Awards or Subawards
  6. Procurement Integrity
  7. Financial Assistance Programs for Infrastructure
  8. Record Retention
  9. Actions to Address Noncompliance
  10. Audits
  11. Payment Information
  12. Procedures for Establishing Indirect Cost Rates
  13. Whole Community Preparedness

Appendix A – FY 2023 EOC Grant Program Project List

A.    Program Description

1.    Issued By

U.S. Department of Homeland Security (DHS)/Federal Emergency Management Agency (FEMA)/Grant Programs Directorate

2.    Assistance Listings Number

97.052

3.    Assistance Listings Title

Emergency Operations Center (EOC) Grant Program

4.    Funding Opportunity Title

Fiscal Year 2023 Emergency Operations Center (EOC) Grant Program

5.    Funding Opportunity Number

FY 2023 EOC Grant ProgramNOFO Number
Region IDHS-23-GPD-052-001-01
Region IIDHS-23-GPD-052-002-01
Region IIIDHS-23-GPD-052-003-01
Region IVDHS-23-GPD-052-004-01
Region VDHS-23-GPD-052-005-01
Region VIDHS-23-GPD-052-006-01
Region VIIDHS-23-GPD-052-007-01
Region VIIIDHS-23-GPD-052-008-01
Region IXDHS-23-GPD-052-009-01
Region XDHS-23-GPD-052-010-01

6.    Authorizing Authority for Program

Section 614 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act (42 U.S.C. 5196c) as amended by section 202 of the Implementing Recommendations of the 9/11 Commission Act of 2007

7.    Appropriation Authority for Program

Consolidated Appropriations Act, 2023 (Pub. L. No. 117-328)

8.    Announcement Type

Initial

9.    Program Category

Preparedness: Community Security

10.    Program Overview, Objectives and Priorities

a.    Overview

The fiscal year (FY) 2023 Emergency Operations Center (EOC) Grant Program is intended to improve emergency management and preparedness capabilities by supporting flexible, sustainable, secure, strategically located, and fully interoperable EOCs with a focus on addressing identified deficiencies and needs. Fully capable emergency operations facilities at the state and local levels are an essential element of a comprehensive national emergency management system and are necessary to ensure coordination and unity of effort among multiple emergency management organizations and across multiple jurisdictions during major disasters or emergencies caused by any hazard. Among the five basic homeland security missions noted in the DHS Strategic Plan for Fiscal Years 2020-2024, the EOC Grant Program supports the goal to Strengthen National Preparedness and Resilience.

The 2022-2026 FEMA Strategic Plan outlines three bold, ambitious goals in order to position FEMA to address the increasing range and complexity of disasters, support the diversity of communities we serve, and complement the nation’s growing expectations of the emergency management community. The EOC Grant Program supports Goal 3: Promote and Sustain a Ready FEMA and a Prepared Nation.

The FY 2023 EOC Grant Program will provide $89,140,285 for equipping, upgrading, or constructing the EOC projects included in Appendix A of this NOFO. Per the National Fire Protection Association, an EOC is defined as a “facility or capability from which direction and control is exercised in an emergency. This type of center or capability is designated to ensure that the capacity exists for leadership to direct and control operations from a centralized facility or capability in the event of an emergency.” “Construction,” as defined in this program, refers to building a new facility or any changes to the footprint of an existing facility, while “upgrading” refers only to internal improvements to an existing facility. 

State Administrative Agencies (SAAs) are the only entities eligible to apply for FY 2023 EOC Grant Program funding. Such applications will be submitted on behalf of the state and local governments (subrecipients) identified to receive funding as outlined in Appendix A of this NOFO. See Section C of this notice for additional program eligibility information and Section D for detailed application instructions.

b.    Objectives

The objective of the FY 2023 EOC Grant Program is to improve EOC operations through funding the EOC projects included in Appendix A of this NOFO. These projects fund equipping, upgrading, and/or construction of EOCs to provide fully capable facilities to support command, control, and coordination of multi-agency responses to major disasters or emergencies.

c.    Priorities

The priorities of the FY 2023 EOC Grant Program are to fund equipping, upgrading, and/or construction of the emergency operations center projects identified in Appendix A of this NOFO.

11.    Performance Measures

Performance metrics for this program are as follows:

  • Percentage of funded projects that result in fully operational emergency operations centers
  • Percentage of funded projects that provide an enhanced level of EOC services and capabilities

FEMA will calculate and analyze the above metrics through a review of recipient Performance Progress Reports and award monitoring to ensure that the funds are expended for their intended purpose and achieve the stated outcomes in the grant application.

B.    Federal Award Information

1.    Available Funding 

$89,140,285

2.    Period of Performance 

36 months

Extensions to the period of performance are allowed. Additional information on period of performance extensions, please refer to Section H of this funding notice.
 
FEMA awards under most programs, including this program, only include one budget period, so it will be same as the period of performance. See 2 C.F.R. § 200.1 for definitions of “budget period” and “period of performance.”

3.    Projected Period of Performance Start Date(s)

No later than 06/01/2023

4.    Projected Period of Performance End Date(s)

No later than 05/31/2026

5.    Funding Instrument Type

Grant

C.    Eligibility Information

1.    Eligible Applicants

Only State Administrative Agencies (SAAs) (on behalf of state and local units of government) with identified projects in Appendix A of this NOFO are eligible to apply.

2.    Applicant Eligibility Criteria

Eligible EOC projects were identified in the Joint Explanatory Statement accompanying the Consolidated Appropriations Act, 2023. Those EOC projects are identified in Appendix A of this NOFO.

3.    Other Eligibility Criteria

a.    National Incident Management System (NIMS) Implementation

Prior to allocation of any federal preparedness awards, recipients must ensure and maintain adoption and implementation of NIMS. The list of objectives used for progress and achievement reporting is on FEMA’s website at NIMS Implementation and Training | FEMA.gov.

Emergency management and incident response activities require carefully managed resources (personnel, teams, facilities, equipment, and/or supplies) to meet incident needs. Utilization of the standardized resource management concepts such as typing, credentialing, and inventorying, promote a strong national mutual aid capability needed to support delivery of core capabilities. Additional information on resource management, NIMS resource typing definitions, job titles, and position qualifications is on FEMA’s website at NIMS Components - Guidance and Tools | FEMA.gov.

FEMA developed the National Incident Management System Guideline for the National Qualification System to describe national credentialing standards and to provide written guidance regarding the use of those standards. This guideline describes credentialing and typing processes and identifies tools that Federal Emergency Response Officials and emergency managers at all levels of government may use both routinely and to facilitate multijurisdictional coordinated responses.

Although state (including territorial), local, tribal, and private sector partners (including nongovernmental organizations) are not required to credential their personnel in accordance with these guidelines, FEMA strongly encourages them to do so to leverage the federal investment in the Federal Information Processing Standards 201 infrastructure and to facilitate interoperability for personnel deployed outside their home jurisdiction.

Additional information about NIMS in general is available on FEMA’s website at National Incident Management System | FEMA.gov.

4.    Cost Share or Match

The FY 2023 EOC Grant Program has a cost share requirement. All award recipients must provide a non-federal entity contribution supporting 25% of the total project costs (federal amount plus cost share amount). The non-federal entity contribution can be cash (hard match) or third-party in-kind (soft match), with the exception of construction activities, which must be a cash (hard) match. In-kind contributions are defined as third-party contributions per 2 C.F.R. § 200.306. The required cost share amount, by project, is included in the project funding table in Appendix A.

All applicants are required to commit to the cost share requirement for each activity under each project at the time of application. The non-federal contribution should be specifically identified for each proposed activity. The non-federal contribution, whether cash or third-party in-kind match, must consist of eligible costs (i.e., same allowability as the federal share).

D.  Application and Submission Information

1.   Key Dates and Times

a.   Application Start Date:                                                 

March 1, 2023

b.   Application Submission Deadline:                                  

April 14, 2023 at 5 p.m. ET

All applications must be received by the established deadline. Prior to application submission, SAAs must coordinate with applicable subrecipients identified in Appendix A to collect the information required for completion of the State’s application and may impose separate deadlines to ensure timely application submission.

The Non-Disaster (ND) Grants System has a date stamp that indicates when an application is submitted. Applicants will receive an electronic message confirming receipt of their submission. For additional information on how an applicant will be notified of application receipt, see the subsection titled “Timely Receipt Requirements and Proof of Timely Submission” in Section D of this NOFO.

FEMA will not review applications that are received after the deadline or consider these late applications for funding. FEMA may, however, extend the application deadline on request for any applicant who can demonstrate that good cause exists to justify extending the deadline. Good cause for an extension may include technical problems outside of the applicant’s control that prevent submission of the application by the deadline, other exigent or emergency circumstances, or statutory requirements for FEMA to make an award.

Applicants experiencing technical problems outside of their control must notify FEMA as soon as possible and before the application deadline. Failure to timely notify FEMA of the issue that prevented the timely filing of the application may preclude consideration of the award. “Timely notification” of FEMA means: prior to the application deadline and within 48 hours after the applicant became aware of the issue.

A list of FEMA contacts can be found in Section G of this NOFO, “DHS Awarding Agency Contact Information.” For additional assistance using the ND Grants System, please contact the ND Grants Service Desk at (800) 865-4076 or NDGrants@fema.dhs.gov. The ND Grants Service Desk is available Monday through Friday, 9:00 AM – 6:00 PM Eastern Time (ET). For programmatic or grants management questions, please contact your FEMA Regional EOC Grant Program Manager. If applicants do not know who to contact or if there are programmatic questions or concerns, please contact the FEMA Grants Information Desk by e-mail at fema-grants-news@fema.dhs.gov OR by phone at (800) 368-6498, Monday through Friday, 9 a.m. – 5 p.m. ET.

c.   Anticipated Award Date:                                    

June 30, 2023


d.   Other Key Dates

The suggested deadlines outlined in the table below apply only to the SAA as the eligible applicant. As noted in Section D.1.b. above, SAAs may impose separate deadlines on the subrecipients identified in Appendix A to ensure timely collection of the information required for application submission.

EventSuggested Deadline for Completion
Initial registration in SAM.gov includes UEI issuanceFour weeks before actual submission deadline
Obtaining a valid Employer Identification Number (EIN)Four weeks before actual submission deadline
Creating an account with login.govFour weeks before actual submission deadline
Registering in SAM or updating SAM registrationFour weeks before actual submission deadline
Registering in Grants.govFour weeks before actual submission deadline
Registering in ND GrantsFour weeks before actual submission deadline
Starting application in Grants.govOne week before actual submission deadline
Submitting application in Grants.govThree days before actual submission deadline
Submitting the final application in ND GrantsBy the submission deadline

2. Agreeing to Terms and Conditions of the Award

By submitting an application, applicants agree to comply with the requirements of this NOFO and the terms and conditions of the award, should they receive an award.

3.   Address to Request Application Package

Initial applications are processed through the Grants.gov portal. Final applications are completed and submitted through FEMA’s Non-Disaster Grants (ND Grants) System. Application forms and instructions are available at Grants.gov. To access these materials, go to Home | Grants.gov.

Hard copies of the NOFO can be downloaded at Grants.gov or obtained via email from the Awarding Office points of contact listed in Section G of this NOFO, “DHS Awarding Agency Contact Information” or by TTY (800) 462-7585. 

4.  Requirements: Obtain a Unique Entity Identifier (UEI) and Register in the System for Award Management (SAM)

Each applicant, unless they have a valid exception under 2 CFR 25.110, must:

  1. Be registered in Sam.Gov before application submission;
  2. Provide a valid Unique Entity Identifier (UEI) in its application; and
  3. Continue to always maintain an active System for Award Management (SAM) registration with current information during the Federal Award process

5.   Steps Required to Obtain a Unique Entity Identifier, Register in the System for Award Management (SAM), and Submit an Application

Applying for an award under this program is a multi-step process and can take four weeks or more to complete. Applicants are encouraged to register early to ensure they meet the required submission deadlines.

Please review the table above for estimated deadlines to complete each of the steps listed. Failure of an applicant to comply with any of the required steps before the deadline for submitting an application may disqualify that application from funding.

To apply for an award under this program, all applicants must:

a.   Apply for, update, or verify their Unique Entity Identifier (UEI) number from SAM.gov and Employer Identification Number (EIN) from the Internal Revenue Service;

b.   In the application, provide an UEI number;

c.   Have an account with login.gov;

d.   Register for, update, or verify their SAM account and ensure the account is active before submitting the application;

e.   Create a Grants.gov account;

f.    Add a profile to a Grants.gov account;

g.   Establish an Authorized Organizational Representative (AOR) in Grants.gov;

h.   Register in ND Grants

I.    Submit an initial application in Grants.gov;

j.    Submit the final application in ND Grants, including electronically signing applicable forms; and

k.   Continue to maintain an active SAM registration with current information at all times during which it has an active federal award or an application or plan under consideration by a federal awarding agency. As part of this, applicants must also provide information on an applicant’s immediate and highest-level owner and subsidiaries, as well as on all predecessors that have been awarded federal contracts or federal financial assistance within the last three years, if applicable.

Specific instructions on how to apply for, update, or verify an UEI number or SAM registration or establish an AOR are included below in the steps for applying through Grants.gov.

Applicants are advised that FEMA may not make a federal award until the applicant has complied with all applicable SAM requirements. Therefore, an applicant’s SAM registration must be active not only at the time of application, but also during the application review period and when FEMA is ready to make a federal award. Further, as noted above, an applicant’s or recipient’s SAM registration must remain active for the duration of an active federal award. If an applicant’s SAM registration is expired at the time of application, expires during application review, or expires any other time before award, FEMA may determine that the applicant is not qualified to receive a federal award and use that determination as a basis for making a federal award to another applicant.

Per 2 C.F.R. § 25.110(c)(2)(iii), if an applicant is experiencing exigent circumstances that prevents it from obtaining an UEI number and completing SAM registration prior to receiving a federal award, the applicant must notify FEMA as soon as possible by contacting askcsid@fema.dhs.gov and providing the details of the circumstances that prevent completion of these requirements. If FEMA determines that there are exigent circumstances and FEMA has decided to make an award, the applicant will be required to obtain an UEI number, if applicable, and complete SAM registration within 30 days of the federal award date.

6.   Electronic Delivery

DHS is participating in the Grants.gov initiative to provide the grant community with a single site to find and apply for grant funding opportunities. DHS encourages or requires applicants to submit their applications online through Grants.gov, depending on the funding opportunity.

For this funding opportunity, FEMA requires applicants to submit initial applications through Grants.gov and a final application through ND Grants.

7.   How to Register to Apply through Grants.gov

a.   General Instructions:

Registering and applying for an award under this program is a multi-step process and requires time to complete. Read the instructions below about registering to apply for FEMA funds. Applicants should read the registration instructions carefully and prepare the information requested before beginning the registration process. Reviewing and assembling the required information before beginning the registration process will alleviate last-minute searches for required information.

The registration process can take up to four weeks to complete. To ensure an application meets the deadline, applicants are advised to start the required steps well in advance of their submission.

Organizations must have an UEI number, an EIN, an active System for Award Management (SAM) registration and Grants.gov account to apply for grants.

Organizations must also have a Grants.gov account to apply for an award under this program. Creating a Grants.gov account can be completed online in minutes, but UEI and SAM registrations may take several weeks. Therefore, an organization's registration should be done in sufficient time to ensure it does not impact the entity's ability to meet required application submission deadlines. Complete organization instructions can be found on Grants.gov here:
Organization Registration | Grants.gov.

If individual applicants are eligible to apply for this grant funding opportunity, refer to Applicant Registration | Grants.gov.

b.   Obtain an UEI Number:

All entities applying for funding, including renewal funding, must have a UEI number. Applicants must enter the UEI number in the applicable data entry field on the SF-424 form.

For more detailed instructions for obtaining a UEI number, refer to SAM.gov.

c.   Obtain Employer Identification Number

All entities applying for funding must provide an Employer Identification Number (EIN). The EIN can be obtained from the IRS by visiting: Apply for an Employer Identification Number (EIN) Online | Internal Revenue Service (irs.gov).

d.   Create a login.gov account:

Applicants must have a login.gov account in order to register with SAM or update their SAM registration. Applicants can create a login.gov account here: Create your account - Login.gov.

Applicants only have to create a login.gov account once. For applicants that are existing SAM users, use the same email address for the login.gov account as with SAM.gov so that the two accounts can be linked.

For more information on the login.gov requirements for SAM registration, refer to SAM.gov | Home.

e.   Register with SAM:

All organizations applying online through Grants.gov must register with SAM. Failure to register with SAM will prevent your organization from applying through Grants.gov. SAM registration must be renewed annually. Organizations will be issued a UEI number with the completed SAM registration.

For more detailed instructions for registering with SAM, refer to Step 2: Register with SAM | Grants.gov.

Note: As a new requirement per 2 C.F.R. § 25.200, applicants must also provide the applicant’s immediate and highest-level owner, subsidiaries, and predecessors that have been awarded federal contracts or federal financial assistance within the last three years, if applicable.

i.    Additional SAM Reminders

Existing SAM.gov account holders should check their account to make sure it is “ACTIVE.” SAM registration should be completed at the very beginning of the application period and should be renewed annually to avoid being “INACTIVE.” Please allow plenty of time before the grant application submission deadline to obtain an UEI number and then to register in SAM. It may be four weeks or more after an applicant submits the SAM registration before the registration is active in SAM, and then it may be an additional 24 hours before FEMA’s system recognizes the information.

It is imperative that the information applicants provide is correct and current. Please ensure that your organization’s name, address, and EIN are up to date in SAM and that the UEI number used in SAM is the same one used to apply for all other FEMA awards. Payment under any FEMA award is contingent on the recipient’s having a current SAM registration.

ii.   Help with SAM

The SAM quick start guide for new recipient registration and SAM video tutorial for new applicants are tools created by the General Services Administration (GSA) to assist those registering with SAM. If applicants have questions or concerns about a SAM registration, please contact the Federal Support Desk at GDIT TSS Service Portal - GDIT Technology Shared Services Portal (fsd.gov) or call toll free (866) 606-8220.

f.    Create a Grants.gov Account:

The next step in the registration process is to create an account with Grants.gov. If applicable, applicants must know their organization’s UEI number to complete this process.

For more information, follow the on-screen instructions or refer to: Applicant Registration | Grants.gov.

See also Section D.9 in this NOFO, “Submitting the Final Application in ND Grants,” for instructions on how to register early in ND Grants.
 

g.   Add a Profile to a Grants.gov Account:

A profile in Grants.gov corresponds to a single applicant organization the user represents (i.e., an applicant) or an individual applicant. If you work for or consult with multiple organizations and have a profile for each, you may log in to one Grants.gov account to access all of your grant applications. To add an organizational profile to your Grants.gov account, if applicable, enter the UEI number for the organization in the UEI field while adding a profile.

For more detailed instructions about creating a profile on Grants.gov, refer to: Add Profile | Grants.gov.

h.   EBiz POC Authorized Profile Roles:

After you register with Grants.gov and create an Organization Applicant Profile, the organization applicant's request for Grants.gov roles and access is sent to the EBiz POC. The EBiz POC will then log in to Grants.gov and authorize the appropriate roles, which may include the Authorized Organization Representative (AOR) role, thereby giving you permission to complete and submit applications on behalf of the organization. You will be able to submit your application online any time after you have been assigned the AOR role.

For more detailed instructions about creating a profile on Grants.gov, refer to EBiz POC Authorizes Profile Roles | Grants.gov.

i.    Track Role Status:

To track your role request, refer to Track Profile Role Status | Grants.gov.

j.   Electronic Signature:

When applications are submitted through Grants.gov, the name of the organization applicant with the AOR role that submitted the application is inserted into the signature line of the application, serving as the electronic signature. The EBiz POC must authorize individuals who are able to make legally binding commitments on behalf of the organization as an AOR; this step is often missed, and it is crucial for valid and timely submissions.

8.   How to Submit an Initial Application to FEMA via Grants.gov

Standard Form 424 (SF-424) is the initial application for this NOFO.

Grants.gov applicants can apply online using a workspace. A workspace is a shared, online environment where members of a grant team may simultaneously access and edit different web forms within an application. For each Notice of Funding Opportunity, you can create individual instances of a workspace. Applicants are encouraged to submit their initial applications in Grants.gov at least seven days before the application deadline.

In Grants.gov, applicants need to submit the following forms:

  • SF-424, Application for Federal Assistance; and
  • Grants.gov Lobbying Form, Certification Regarding Lobbying.

Below is an overview of applying on Grants.gov. For access to complete instructions on how to apply for opportunities using Workspace, refer to Workspace Overview | Grants.gov.

a.   Create a Workspace:

Creating a workspace allows you to complete it online and route it through your organization for review before submitting.

b.   Complete a Workspace:

Add participants to the workspace to work on the application together, complete all the required forms online or by downloading PDF versions, and check for errors before submission.

c.   Adobe Reader:

If you decide not to apply by filling out webforms you can download individual PDF forms in Workspace so that they will appear similar to other Standard or DHS forms. The individual PDF forms can be downloaded and saved to your local device storage, network drive(s), or external drives, then accessed through Adobe Reader.

NOTE: Visit the Adobe Software Compatibility page on Grants.gov to download the appropriate version of the software at Adobe Software Compatibility | Grants.gov.

d.   Mandatory Fields in Forms: 

In the forms, you will note fields marked with an asterisk and a different background color. These fields are mandatory fields that must be completed to successfully submit your application.

e.   Complete SF-424 Fields First:

The forms are designed to fill in common required fields across other forms, such as the applicant name, address, and UEI number. To trigger this feature, an applicant must complete the SF-424 information first. Once it is completed, the information will transfer to the other forms.

f.    Submit a Workspace:

An application may be submitted through workspace by clicking the “Sign and Submit” button on the Manage Workspace page, under the Forms tab. Grants.gov recommends submitting your application package at least 24-48 hours prior to the close date to provide you with time to correct any potential technical issues that may disrupt the application submission.

g.   Track a Workspace:

After successfully submitting a workspace package, a Grants.gov Tracking Number (GRANTXXXXXXXX) is automatically assigned to the application. The number will be listed on the confirmation page that is generated after submission. Using the tracking number, access the Track My Application page under the Applicants tab or the Details tab in the submitted workspace.

h.   Additional Training and Applicant Support:

For additional training resources, including video tutorials, refer to: Applicant Training | Grants.gov.

Grants.gov provides applicants 24/7 (except federal holidays) support via the toll-free number (800) 518-4726, email at support@grants.gov and the website at Support | Grants.gov. For questions related to the specific grant opportunity, contact the number listed in the application package of the grant you are applying for.

If you are experiencing difficulties with your submission, it is best to call the Grants.gov Support Center and get a ticket number. The Support Center ticket number will assist FEMA with tracking your issue and understanding background information on the issue.

9.   Submitting the Final Application in ND Grants

After submitting the initial application in Grants.gov, eligible applicants will be notified by FEMA and asked to proceed with submitting their complete application package in ND Grants. Applicants can register early with ND Grants and are encouraged to begin their ND Grants registration at the time of this announcement or, at the latest, seven days before the application deadline. Early registration will allow applicants to have adequate time to start and complete their applications.

Applicants needing assistance registering for the ND Grants system should contact ndgrants@fema.dhs.gov or (800) 865-4076, Monday through Friday, 9:00 AM – 6:00 PM ET. For step-by-step directions on using the ND Grants system and other guides, please see Non-Disaster Grants Management System | FEMA.gov.

In ND Grants, applicants will be prompted to submit the standard application information and any program-specific information required as described in Section D.10 of this NOFO, “Content and Form of Application Submission.” The Standard Forms (SF) are auto generated in ND Grants, but applicants may access these forms in advance through the Forms tab under the SF-424 family on Grants.gov. Applicants should review these forms before applying to ensure they have all the information required.

For additional application submission requirements, including program-specific requirements, please refer to the subsection titled “Content and Form of Application Submission” under Section D of this NOFO.

10.   Timely Receipt Requirements and Proof of Timely Submission

As application submission is a two-step process, the applicant with the AOR role who submitted the application in Grants.gov will receive an acknowledgement of receipt and a tracking number (GRANTXXXXXXXX) from Grants.gov with the successful transmission of its initial application. This notification does not serve as proof of timely submission, as the application is not complete until it is submitted in ND Grants. Applicants can also view the ND Grants Agency Tracking Number by accessing the Details tab in the submitted workspace section in Grants.gov, under the Agency Tracking Number column. Should the Agency Tracking Number not appear, the application has not yet migrated from Grants.gov into the ND Grants System. Please allow 24 hours for your ND Grants application tracking number to migrate.

All applications must be received in ND Grants by 5:00 PM ET on the application deadline. Proof of timely submission is automatically recorded by ND Grants. An electronic date/time stamp is generated within the system when the application is successfully received by ND Grants. Additionally, the applicant(s) listed as contacts on the application will receive a system-generated email to confirm receipt.

11. Content and Form of Application Submission

a.   Standard Required Application Forms and Information

The following forms or information are required to be submitted in either Grants.gov or ND Grants. The Standard Forms (SF) are submitted either through Grants.gov, through forms generated in ND Grants, or as an attachment in ND Grants. Applicants may also access the SFs at SF-424 Family | Grants.gov.

i.    Grants.Gov

  • SF-424, Application for Federal Assistance, initial application submitted through Grants.gov
  • Grants.gov Lobbying Form, Certification Regarding Lobbying, submitted through Grants.gov

ii.   ND Grants

  • SF-424A, Budget Information (Non-Construction), submitted via the forms generated by ND Grants
    • For construction under an award, submit SF-424C, Budget Information (Construction), submitted via the forms generated by ND Grants, in addition to or instead of SF-424A
  • SF-424B, Standard Assurances (Non-Construction), submitted via the forms generated by ND Grants
    • For construction under an award, submit SF-424D, Standard Assurances (Construction), submitted via the forms generated by ND Grants, in addition to or instead of SF-424B
  • SF-LLL, Disclosure of Lobbying Activities, submitted via the forms generated by ND Grants
  • Indirect Cost Agreement or Proposal, submitted as an attachment in ND Grants if the budget includes indirect costs and the applicant is required to have an indirect cost rate agreement or proposal. If the applicant does not have or is not required to have an indirect cost rate agreement or proposal, please see Section D.13 of this NOFO, “Funding Restrictions and Allowable Costs,” for further information regarding allowability of indirect costs and whether alternatives to an indirect cost rate agreement or proposal might be available or contact the relevant FEMA staff identified in Section G of this NOFO, “DHS Awarding Agency Contact Information” for further instructions.

Generally, applicants have to submit either the non-construction forms (i.e., SF-424A and SF-424B) or construction forms (i.e., SF-424C and SF-424D), meaning that applicants that only have construction work and do not have any non-construction work need only submit the construction forms (i.e., SF-424C and SF-424D) and not the non-construction forms (i.e., SF-424A and SF-424B), and vice versa. However, applicants who have both construction and non-construction work under this program need to submit both the construction and non-construction forms.

b.   Program-Specific Required Forms and Information

The following program-specific forms or information are required to be submitted in ND Grants:

  • As part of the FY 2023 EOC Grant Program application process, applicants must develop a formal Investment Justification (IJ) that addresses the construction, upgrading, or equipping activities and costs. FEMA has developed an Excel-based template that establishes the required IJ content and helps ensure that submissions are organized in a consistent manner while addressing key data requirements. Use of the template is not mandatory but recommended to ensure all appropriate information is submitted. If applicants choose to not use the template, they must ensure their application submission includes all fields and data elements that are included in the template. All applications must use the following file naming convention when submitting required documents as part of the FY 2023 EOC Grant Program: “FY 2023 EOC <State Abbreviation> - <EOC Name>.”

12. Intergovernmental Review

An intergovernmental review may be required. Applicants must contact their state’s Single Point of Contact (SPOC) to comply with the state’s process under Executive Order 12372

(See Executive Orders | National Archives; Intergovernmental Review (SPOC List) (whitehouse.gov)

 

13. Funding Restrictions and Allowable Costs

All costs charged to awards covered by this NOFO must comply with the Uniform Administrative Requirements, Cost Principles, and Audit Requirements at 2 C.F.R. Part 200, unless otherwise indicated in this NOFO, or the terms and conditions of the award. This includes, among other requirements, that costs must be incurred, and products and services must be delivered, within the period of performance of the award, with the exception of approved pre-award costs (see Section 13.b Pre-award Costs). Also see 2 C.F.R. § 200.403(h) (referring to budget periods, which for FEMA awards is the same as the period of performance). For the EOC Grant Program, the budget period is the same as the period of performance.

In general, the Cost Principles establish standards for the allowability of costs, provide detailed guidance on the cost accounting treatment of costs as direct or administrative costs, and set forth allowability principles for selected items of cost. More specifically, except as otherwise stated in this NOFO, the terms and condition of an award, or other program materials, costs charged to awards covered by this NOFO must be consistent with the Cost Principles for Federal Awards located at 2 C.F.R. Part 200, Subpart E. In order to be allowable, all costs charged to a FEMA award or applied to the cost share must be reasonable in nature and amount and allocable to the particular FEMA award.

Additionally, all costs charged to awards must comply with the grant program’s applicable statutes, policies, requirements in this NOFO as well as with the terms and conditions of the award. If FEMA staff identify costs that are inconsistent with any of these requirements, these costs may be disallowed, and FEMA may recover funds as appropriate, consistent with applicable laws, regulations, and policies.

As part of those requirements, grant recipients and subrecipients may only use federal funds or funds applied to a cost share for the purposes set forth in this NOFO and the terms and conditions of the award, and those costs must be consistent with the statutory authority for the award.

Grant funds may not be used for matching funds for other federal grants/cooperative agreements, lobbying, or intervention in federal regulatory or adjudicatory proceedings. In addition, federal funds may not be used to sue the federal government or any other government entity.

a.   Prohibitions on Expending FEMA Award Funds for Covered Telecommunications Equipment or Services

Recipients and subrecipients of FEMA federal financial assistance are subject to the prohibitions described in section 889 of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (FY 2019 NDAA), Pub. L. No. 115-232 (2018) and 2 C.F.R. §§ 200.216, 200.327, 200.471, and Appendix II to 2 C.F.R. Part 200. Beginning August 13, 2020, the statute – as it applies to FEMA recipients, subrecipients, and their contractors and subcontractors – prohibits obligating or expending federal award funds on certain telecommunications and video surveillance products and contracting with certain entities for national security reasons.

Guidance is available at Prohibitions on Expending FEMA Award Funds for Covered Telecommunications Equipment or Services, FEMA Policy  #405-143-1, or superseding document.

Additional guidance is available at Contract Provisions Guide: Navigating Appendix II to Part 200 - Contract Provisions for Non-Federal Entity Contracts Under Federal Awards (fema.gov).

Effective August 13, 2020, FEMA recipients and subrecipients may not use any FEMA funds under open or new awards to:

  1. Procure or obtain any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology of any system;
  2. Enter into, extend, or renew a contract to procure or obtain any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology of any system; or
  3. Enter into, extend, or renew contracts with entities that use covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

I. Replacement Equipment and Services

FEMA grant funding may be permitted to procure replacement equipment and services impacted by this prohibition, provided the costs are otherwise consistent with the requirements of the NOFO.

ii.   Definitions

Per section 889(f)(2)-(3) of the FY 2019 NDAA and 2 C.F.R. § 200.216, covered telecommunications equipment or services means:

i.    Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation, (or any subsidiary or affiliate of such entities);

ii.   For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);

iii.  Telecommunications or video surveillance services provided by such entities or using such equipment; or

iv.  Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the People’s Republic of China.

Examples of the types of products covered by this prohibition include phones, internet, video surveillance, and cloud servers when produced, provided, or used by the entities listed in the definition of “covered telecommunications equipment or services.” See 2 C.F.R. § 200.471.

b.   Pre-award Costs

Pre-award costs are allowable only with the prior written approval of DHS/FEMA and if they are included in the award agreement. To request pre-award costs, a written request must be included with the application and be signed by the AOR. The request letter must include:

  • an explanation of the pre-award costs incurred, including a justification for why the costs should be deemed allowable; and
  • an itemized budget break-out that details all claimed pre-award costs, including dates incurred, to clearly distinguish them from post-award costs.

Recipients and subrecipients are cautioned that an Environmental Planning and Historic Preservation (EHP) review is required for all federally funded projects. Most EOCGP-funded projects that involve construction activities (including site prep and any ground disturbance activities) or modifications to existing buildings will require a full EHP review. Furthermore, the EHP review process usually must be completed before the project may begin. In some limited circumstances FEMA can conduct an after-the-fact (ATF) EHP review, which would retroactively provide approval for EHP-related activities and would allow grant funds to pay for pre-award costs for these activities. However, an ATF review may find EHP compliance issues that cannot be remedied because construction or installation had already begun. Such situations may compel FEMA to decline to provide pre-award costs, and even revoke federal funding for those portions of the project that fail to meet the EHP compliance requirements. See Section F.3.c of this NOFO for additional EHP guidance.

   c.  Management and Administration (M&A) Costs

M&A costs are allowed for activities directly related to the management and administration of the award, such as financial management, reporting, and program and financial monitoring. Some examples of M&A costs include grants management training for M&A staff, equipment and supplies for M&A staff to administer the grant award, travel costs for M&A staff to attend conferences or training related to the grant program, travel costs for the M&A staff to conduct subrecipient monitoring, contractual services to support the M&A staff with M&A activities, and auditing costs related to the grant award to the extent required or permitted by statute or 2 C.F.R. Part 200. Characteristics of M&A expenses can include the following: 1) direct costs that are incurred to administer a particular Federal award; 2) identifiable and unique to each Federal award; 3) charged based on the activity performed for that particular Federal award; and 4) not duplicative of the same costs that are included in the approved Indirect Cost Rate Agreement, if applicable.

State recipients may use up to 4.8336663% of the total award amount (the federal share) of each subaward project for their M&A. This figure is based on the total dollar amount ($15,960,933) appropriated by Congress to support M&A costs for state recipients under both the FY 2023 EOC and Pre-Disaster Mitigation Grant Programs. This 4.8336663% figure excludes the amount of any required non-federal match and is not subject to any kind of non-federal cost-share. Any funds retained must be used solely for M&A purposes associated with the EOCGP award. Per the Joint Explanatory Statement accompanying the Consolidated Appropriations Act, 2023, the Recipients’ M&A funding is not part of the subaward project award funding. The Joint Explanatory Statement also notes that State recipients may use other eligible funds for M&A.

Subrecipients may use up to 5% of the funding passed through by the state solely for M&A purposes associated with the EOCGP award.

d.   Indirect Facilities & Administrative (F&A) Costs

Indirect costs are allowable under this program as described in 2 C.F.R. Part 200, including 2 C.F.R. § 200.414. Applicants with a current negotiated indirect cost rate agreement that desire to charge indirect costs to an award must provide a copy of their negotiated indirect cost rate agreement at the time of application. Not all applicants are required to have a current negotiated indirect cost rate agreement. Applicants that are not required by 2 C.F.R. Part 200 to have a negotiated indirect cost rate agreement but are required by 2 C.F.R. Part 200 to develop an indirect cost rate proposal must provide a copy of their proposal at the time of application. Applicants who do not have a current negotiated indirect cost rate agreement (including a provisional rate) and wish to charge the de minimis rate must reach out to the FEMA Regional Grants Management Specialist for further instructions. Applicants who wish to use a cost allocation plan in lieu of an indirect cost rate must also reach out to the FEMA Regional Grants Management Specialist for further instructions. Post-award requests to charge indirect costs will be considered on a case-by-case basis and based upon the submission of an agreement or proposal as discussed above or based upon on the de minimis rate or cost allocation plan, as applicable. See Section H.12 of this NOFO for additional information on the procedures for establishing an indirect cost rate.

 

f.   Other Direct Costs

I. Planning

Planning costs to support the EOC construction or upgrading activities are allowable. These planning activities include the following:

  1. Developing plans, protocols, or procedures for the operation and use related to new capabilities as a result of the construction or upgrading activities;
  2. Conducting physical and cyber security assessments;
  3. Ensuring EOC continuity of operations; and
  4. Analyzing constructed or renovated space to support the design and implementation of protection systems (e.g., fire protection and suppression, atmospheric filtration, explosives mitigation).

II. Equipment 

Only equipment integral to EOC construction and upgrading activities is allowable. The allowable equipment categories for the FY 2023 EOC Grant Program are listed on the Authorized Equipment List (AEL). Although an item may be included within an allowable category on the list, the equipment must also directly support the function and operation of the EOC to be considered allowable.

The select allowable equipment includes equipment from the following AEL categories:

  • Explosive Device Mitigation and Remediation (Category 2)
  • Information Technology (Category 4)
  • Cybersecurity Enhancement Equipment (Category 5)
  • Interoperable Communications Equipment (Category 6)
  • Power Equipment (Category 10)
  • Chemical, Biological, Radiological, Nuclear, and Explosive (CBRNE) Reference Materials (Category 11)
  • Physical Security Enhancement Equipment (Category 14)
  • CBRNE Logistical Support Equipment (Category 19)
  • Other Authorized Equipment (Category 21)

If applicants have questions concerning the eligibility of equipment not specifically addressed in the AEL, they should contact their FEMA Regional EOC Grant Program Manager through the FEMA Grants Information Desk at fema-grants-news@fema.dhs.gov OR (800) 368-6498 for clarification,  Monday through Friday, 9 a.m. – 5 p.m. ET.

FEMA will consider requests to purchase equipment that is not listed in the AEL on a case-by-case basis. Such requests should be submitted in writing to the applicable FEMA Regional Grant Program Office. FEMA’s review and approval of such requests will involve both the FEMA regional office and headquarters program staff to ensure nationwide consistency in the decision-making process and to support any necessary updates to the AEL.

Applicants should analyze the cost benefits of purchasing versus leasing equipment, especially high-cost items and those subject to rapid technological advances. Large equipment purchases must be identified and explained. For more information regarding property management standards for equipment, please reference 2 C.F.R. Part 200, including 2 C.F.R. §§ 200.310, 200.313, and 200.316. Also see 2 C.F.R. §§ 200.216, 200.471, and FEMA Policy #405-143-1, or successor policy, regarding prohibitions on covered telecommunications equipment or services.

Recipients and sub-recipients that are using FY 2023 EOC Grant Program funds to support emergency communications activities must comply with the SAFECOM Guidance on Emergency Communications Grants, including provisions on technical standards that ensure and enhance interoperable communications. This SAFECOM Guidance can be found at Funding Resources | CISA.

Recipients and sub-recipients are required to provide the AEL number for all communications equipment purchased with grant award funding (plus a description of the equipment and the quantity purchased of each item) to the FEMA GPD once items are procured as part of periodic programmatic grant reporting.

III. Construction and Upgrading

“Construction,” as defined in this program, refers to building a new facility or any changes to the footprint of an existing facility, while “upgrading” refers to internal improvements to an existing facility. For EOC projects that involve construction or upgrading of multipurpose facilities, such as public safety facilities, police/fire stations, etc., EOCGP funding may only be used for those parts of the facility that are directly associated with the EOC. For new facility construction, the use of EOCGP funds should be limited to the proportionate facility construction cost, generally based on the square footage (floor space) of the EOC compared to the square footage of the entire facility.

All proposed construction and upgrading activities must undergo an Environmental Planning and Historic Preservation (EHP) review, including approval of the review from FEMA, prior to undertaking any action related to the project. Failure of a grant recipient to meet these requirements may jeopardize Federal funding. See Section F.3.c of this NOFO for more information.

E.  Application Review Information

1.   Application Evaluation Criteria

a.   Programmatic Criteria

Applications will be reviewed to ensure completeness, adherence to programmatic guidelines, and cost allowability.

b.   Financial Integrity Criteria

Prior to making a federal award, FEMA is required by 31 U.S.C. § 3354, as enacted by the Payment Integrity Information Act of 2019, Pub. L. No. 116-117 (2020); 41 U.S.C. § 2313; and 2 C.F.R. § 200.206 to review information available through any Office of Management and Budget (OMB)-designated repositories of governmentwide eligibility qualification or financial integrity information, including whether the applicant is suspended or debarred. FEMA may also pose additional questions to the applicant to aid in conducting the pre-award risk review. Therefore, application evaluation criteria may include the following risk-based considerations of the applicant:

  1. Financial stability;
  2. Quality of management systems and ability to meet management standards;
  3. History of performance in managing federal award;
  4. Reports and findings from audits; and
  5. Ability to effectively implement statutory, regulatory, or other requirements.

c.   Supplemental Financial Integrity Criteria and Review

Prior to making a federal award where the anticipated total federal share will be greater than the simplified acquisition threshold, currently $250,000:

  1.  FEMA is required to review and consider any information about the applicant, including information on the applicant’s immediate and highest-level owner, subsidiaries, and predecessors, if applicable, that is in the designated integrity and performance system accessible through the System for Award Management (SAM), which is currently the Federal Awardee Performance and Integrity Information System (FAPIIS).
  2. An applicant, at its option, may review information in FAPIIS and comment on any information about itself that a federal awarding agency previously entered.
  3. FEMA will consider any comments by the applicant, in addition to the other information in FAPIIS, in making a judgment about the applicant’s integrity, business ethics, and record of performance under federal awards when completing the review of risk posed by applicants as described in 2 C.F.R. § 200.206.

2.   Review and Selection Process

Applications will be reviewed to ensure compliance with administrative application requirements, and that all proposed activities and budget line-items are allowable under this program.

F.   Federal Award Administration Information

1.   Notice of Award

Before accepting the award, the AOR and recipient should carefully read the award package. The award package includes instructions on administering the grant award and the terms and conditions associated with responsibilities under federal awards. Recipients must accept all conditions in this NOFO as well as any specific terms and conditions in the Notice of Award to receive an award under this program.

Notification of award approval is made through the ND Grants system through an automatic electronic mail to the recipient’s authorized official listed in the initial application. The recipient should follow the directions in the notification to confirm acceptance of the award.

Recipients must accept their awards no later than 60 days from the award date. The recipient shall notify FEMA of its intent to accept and proceed with work under the award or provide a notice of intent to decline through the ND Grants system. For instructions on how to accept or decline an award in the ND Grants system, please see the ND Grants Grant Recipient User Guide, which is available at Non-Disaster Grants Management System | FEMA.gov along with other ND Grants materials.

Funds will remain on hold until the recipient accepts the award through the ND Grants system and all other conditions of the award have been satisfied or until the award is otherwise rescinded. Failure to accept a grant award within the 60-day timeframe may result in a loss of funds.

2.   Pass-Through Requirements

The SAA must pass-through 100% of funding to the subrecipients identified in Appendix A of this NOFO. Separate funding has been set aside for Recipient M&A costs. See Section D.13.c for more information.

3.   Administrative and National Policy Requirements

In addition to the requirements of in this section and in this NOFO, FEMA may place specific terms and conditions on individual awards in accordance with 2 C.F.R. Part 200.

a.   DHS Standard Terms and Conditions

All successful applicants for DHS grant and cooperative agreements are required to comply with DHS Standard Terms and Conditions, which are available online at: DHS Standard Terms and Conditions.

The applicable DHS Standard Terms and Conditions will be those in effect at the time the award was made. What terms and conditions will apply for the award will be clearly stated in the award package at the time of award.

b.   Ensuring the Protection of Civil Rights

As the Nation works towards achieving the National Preparedness Goal, it is important to continue to protect the civil rights of individuals. Recipients and subrecipients must carry out their programs and activities, including those related to the building, sustainment, and delivery of core capabilities, in a manner that respects and ensures the protection of civil rights for protected populations.

Federal civil rights statutes, such as Section 504 of the Rehabilitation Act of 1973 and Title VI of the Civil Rights Act of 1964, along with DHS and FEMA regulations, prohibit discrimination on the basis of race, color, national origin, sex, religion, age, disability, limited English proficiency, or economic status in connection with programs and activities receiving federal financial assistance from FEMA.

The DHS Standard Terms and Conditions include a fuller list of the civil rights provisions that apply to recipients. These terms and conditions can be found in the DHS Standard Terms and Conditions. Additional information on civil rights provisions is available at External Civil Rights Division | FEMA.gov.

Monitoring and oversight requirements in connection with recipient compliance with federal civil rights laws are also authorized pursuant to 44 C.F.R. Part 7.

In accordance with civil rights laws and regulations, recipients and subrecipients must ensure the consistent and systematic fair, just, and impartial treatment of all individuals, including individuals who belong to underserved communities that have been denied such treatment.

c.   Environmental Planning and Historic Preservation (EHP) Compliance

As a federal agency, FEMA is required to consider the effects of its actions on the environment and historic properties to ensure that all activities and programs funded by FEMA, including grant-funded projects, comply with federal EHP laws, Executive Orders, regulations, and policies, as applicable.

All non-critical new construction or substantial improvement of structures in a Special Flood Hazard Area must, at a minimum, apply the flood elevations of the Federal Flood Risk Management Standard’s Freeboard Value Approach unless doing so would cause the project to be unable to meet applicable program cost-effectiveness requirements. All other types of projects may choose to apply the flood elevations of the Federal Flood Risk Management Standard’s Freeboard Value Approach. See Executive Order (EO) 14030, Climate-Related Financial Risk and FEMA Policy #-206-21-0003, Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Programs (Interim) (fema.gov)

All GPD actions, including grant-funded actions, must comply with National Flood Insurance Program criteria or any more restrictive federal, state, or local floodplain management standards or building code (44 CFR § 9.11(d)(6)). All GPD-funded non-critical actions in 1% annual chance floodplains (also known as 100-year floodplains) that involve new construction or substantial improvement of structures must be elevated, at a minimum, to the lower of:

  • Two feet above the 1% annual chance flood elevation (also known as the base flood elevation), in accordance with the Federal Flood Risk Management Standard (FFRMS) “Freeboard Value Approach” (FVA); or
  • The 0.2% annual chance flood elevation. Where 0.2% annual chance flood elevations are not available, such actions must be elevated to at least two feet above the 1% annual chance flood elevation.

All GPD-funded critical actions in 0.2% annual chance floodplains (also known as 500-year floodplains) that involve new construction or substantial improvement of structures must be elevated, at a minimum, to the higher of:

  • Three feet above the 1% annual chance flood elevation; or
  • The 0.2% annual chance flood elevation. Where 0.2% annual chance flood elevations are not available, such actions must be elevated to at least three feet above the 1% annual chance flood elevation.

See Executive Order (EO) 11988, Floodplain Management, as amended by EO 13690, Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input.

Recipients and subrecipients proposing projects that have the potential to impact the environment, including, but not limited to, the construction of communication towers, modification or renovation of existing buildings, structures, and facilities, or new construction including replacement of facilities, must participate in the FEMA EHP review process. The EHP review process involves the submission of a detailed project description along with any supporting documentation requested by FEMA in order to determine whether the proposed project has the potential to impact environmental resources or historic properties.

In some cases, FEMA is also required to consult with other regulatory agencies and the public in order to complete the review process. Federal law requires EHP review to be completed before federal funds are released to carry out proposed projects. FEMA may not be able to fund projects that are not incompliance with applicable EHP laws, Executive Orders, regulations, and policies.

DHS and FEMA EHP policy is found in directives and instructions available on the FEMA.gov EHP page, the FEMA website page that includes documents regarding EHP responsibilities and program requirements, including implementation of the National Environmental Policy Act and other EHP regulations and Executive Orders.

The GPD EHP screening form is located at: FEMA Form. Additionally, all recipients under this funding opportunity are required to comply with the FEMA GPD EHP Policy Guidance, FEMA Policy #108-023-1.

d.   National Incident Management System (NIMS) Implementation

In expending funds under this program, recipients that are state, local, tribal, or territorial governments must ensure and maintain adoption and implementation of NIMS. The state, local, tribal, or territorial government must show adoption of NIMS during any point of the period of performance. The list of objectives used for progress and achievement reporting is at NIMS Implementation and Training | FEMA.gov.

Emergency management and incident response activities require carefully managed resources (personnel, teams, facilities, equipment, and/or supplies) to meet incident needs. Using standardized resource management concepts such as typing, credentialing, and inventorying, promote a strong national mutual aid capability needed to support delivery of core capabilities. Additional information on resource management, NIMS resource typing definitions, job titles, and position qualifications is on FEMA’s website at NIMS Components - Guidance and Tools | FEMA.gov.

FEMA developed the National Incident Management System Guideline for the National Qualification System to describe national credentialing standards and to provide written guidance regarding the use of those standards. This guideline describes credentialing and typing processes and identifies tools which Federal Emergency Response Officials and emergency managers at all levels of government may use both routinely and to facilitate multijurisdictional coordinated responses.

Although state, local, tribal, and private sector partners (including nongovernmental organizations) are not required to credential their personnel in accordance with these guidelines, FEMA strongly encourages them to do so to leverage the federal investment in the Federal Information Processing Standards 201 infrastructure and to facilitate interoperability for personnel deployed outside their home jurisdiction.

Additional information about NIMS in general is available at National Incident Management System | FEMA.gov.

4.   Reporting

Recipients are required to submit various financial and programmatic reports as a condition of award acceptance. Future awards and funds drawdown may be withheld if these reports are delinquent.

a.   Financial Reporting Requirements

Federal Financial Report (FFR)

Recipients must report obligations and expenditures through the FFR form (SF-425) to FEMA.

Recipients may review the Federal Financial Reporting Form (FFR) (SF-425) at Post-Award Reporting Forms | Grants.gov.

Recipients must file the FFR electronically using the Payment and Reporting Systems (PARS).

FFR Reporting Periods and Due Dates

An FFR must be submitted quarterly throughout the POP, including partial calendar quarters, as well as in periods where no grant award activity occurs. The final FFR is due within 120 calendar days after the end of the POP. Future awards and fund drawdowns may be withheld if these reports are delinquent, demonstrate lack of progress, or are insufficient in detail.

Except for the final FFR due at 120 days after the end of the POP for purposes of closeout, the following reporting periods and due dates apply for the FFR:

Reporting PeriodReport Due Date
October 1 – December 31January 30
January 1 – March 31April 30
April 1 – June 30July 30
July 1 – September 30October 30

b. Programmatic Performance Reporting Requirements

Performance Progress Report (PPR)

Recipients are responsible for providing updated performance reports on a biannual basis as an attachment in ND Grants. The PPR must include:

  • A brief narrative of overall project(s) status;
  • A summary of project expenditures; and
  • A description of any potential issues that may affect project completion.

c.   Program Performance Reporting Periods and Due Dates

The following reporting periods and due dates apply for the PPR:

Reporting PeriodReport Due Date
January 1 – June 30July 30
July 1 – December 31January 30

d.   Closeout Reporting Requirements

I.    Closeout Reporting

Within 120 calendar days after the end of the period of performance for the prime award or after an amendment has been issued to close out an award before the original POP ends, recipients must liquidate all financial obligations and must submit:

  1. The final request for payment, if applicable;
  2. The final FFR (SF-425);
  3. The final progress report detailing all accomplishments, including a narrative summary of the impact of those accomplishments throughout the period of performance;
  4. A qualitative narrative summary of the impact of those accomplishments throughout the entire POP; and
  5. Other documents required by this NOFO, terms and conditions of the award, or other FEMA guidance.

In addition, pass-through entities are responsible for closing out their subawards as described in 2 C.F.R. § 200.344; subrecipients are still required to submit closeout materials within 90 calendar days of the period of performance end date. When a subrecipient completes all closeout requirements, pass-through entities must promptly complete all closeout actions for subawards in time for the recipient to submit all necessary documentation and information to FEMA during the closeout of the prime award.

After the prime award closeout reports have been reviewed and approved by FEMA, a closeout notice will be completed to close out the grant. The notice will indicate the period of performance as closed, list any remaining funds that will be deobligated, and address the requirement of maintaining the grant records for at least three years from the date of the final FFR. The record retention period may be longer, such as due to an audit or litigation, for equipment or real property used beyond the period of performance, or due to other circumstances outlined in 2 C.F.R. § 200.334.

The recipient is responsible for refunding to FEMA any balances of unobligated cash that FEMA paid that are not authorized to be retained per 2 C.F.R. § 200.344(d).

ii.   Administrative Closeout

Administrative closeout is a mechanism for FEMA to unilaterally move forward with closeout of an award using available award information in lieu of final reports from the recipient per 2 C.F.R. § 200.344(h)-(i). It is a last resort available to FEMA, and if FEMA needs to administratively close an award, this may negatively impact a recipient’s ability to obtain future funding. This mechanism can also require FEMA to make cash or cost adjustments and ineligible cost determinations based on the information it has, which may result in identifying a debt owed to FEMA by the recipient.

When a recipient is not responsive to FEMA’s reasonable efforts to collect required reports needed to complete the standard closeout process, FEMA is required under 2 C.F.R. § 200.344(h) to start the administrative closeout process within the regulatory timeframe. FEMA will make at least three written attempts to collect required reports before initiating administrative closeout. If the recipient does not submit all required reports in accordance with 2 C.F.R. § 200.344, this NOFO, and the terms and conditions of the award, FEMA must proceed to administratively close the award with the information available within one year of the period of performance end date. Additionally, if the recipient does not submit all required reports within one year of the period of performance end date, per 2 C.F.R. § 200.344(i), FEMA must report in FAPIIS the recipient’s material failure to comply with the terms and conditions of the award.

If FEMA administratively closes an award where no final FFR has been submitted, FEMA uses that administrative closeout date in lieu of the final FFR submission date as the start of the record retention period under 2 C.F.R. § 200.334.

In addition, if an award is administratively closed, FEMA may decide to impose remedies for noncompliance per 2 C.F.R. § 200.339, consider this information in reviewing future award applications, or apply special conditions to existing or future awards.

e.  Additional Reporting Requirements

I. Disclosing Information per 2 C.F.R. § 180.335

This reporting requirement pertains to disclosing information related to government-wide suspension and debarment requirements. Before a recipient enters into a grant award with FEMA, the recipient must notify FEMA if it knows if it or any of the recipient’s principals under the award fall under one or more of the four criteria listed at 2 C.F.R. § 180.335:

  1. Are presently excluded or disqualified;
  2. Have been convicted within the preceding three years of any of the offenses listed in 2 C.F.R. § 180.800(a) or had a civil judgment rendered against it or any of the recipient’s principals for one of those offenses within that time period;
  3. Are presently indicted for or otherwise criminally or civilly charged by a governmental entity (federal, state or local) with commission of any of the offenses listed in 2 C.F.R. § 180.800(a); or
  4. Have had one or more public transactions (federal, state, or local) terminated within the preceding three years for cause or default.

At any time after accepting the award, if the recipient learns that it or any of its principals falls under one or more of the criteria listed at 2 C.F.R. § 180.335, the recipient must provide immediate written notice to FEMA in accordance with 2 C.F.R. § 180.350.

This reporting requirement pertains to disclosing information related to government-wide suspension and debarment requirements. Before a recipient enters into a grant award with FEMA, the recipient must notify FEMA if it knows if it or any of the recipient’s principals under the award fall under one or more of the four criteria listed at 2 C.F.R. § 180.335:

  1. Are presently excluded or disqualified;
  2. Have been convicted within the preceding three years of any of the offenses listed in 2 C.F.R. § 180.800(a) or had a civil judgment rendered against it or any of the recipient’s principals for one of those offenses within that time period;
  3.  Are presently indicted for or otherwise criminally or civilly charged by a governmental entity (federal, state or local) with commission of any of the offenses listed in 2 C.F.R. § 180.800(a); or
  4. Have had one or more public transactions (federal, state, or local) terminated within the preceding three years for cause or default.

At any time after accepting the award, if the recipient learns that it or any of its principals falls under one or more of the criteria listed at 2 C.F.R. § 180.335, the recipient must provide immediate written notice to FEMA in accordance with 2 C.F.R. § 180.350.

ii.   Reporting of Matters Related to Recipient Integrity and Performance

Per 2 C.F.R. Part 200, Appendix I § F.3, the additional post-award reporting requirements in 2 C.F.R. Part 200, Appendix XII may apply to applicants who, if upon becoming recipients, have a total value of currently active grants, cooperative agreements, and procurement contracts from all federal awarding agencies that exceeds $10,000,000 for any period of time during the period of performance of an award under this funding opportunity.

Recipients that meet these criteria must maintain current information reported in FAPIIS about civil, criminal, or administrative proceedings described in paragraph 2 of Appendix XII at the reporting frequency described in paragraph 4 of Appendix XII.

iii. Single Audit Report

For audits of fiscal years beginning on or after December 26, 2014, recipients that expend $750,000 or more from all federal funding sources during their fiscal year are required to submit an organization-wide financial and compliance audit report, also known as the single audit report.

The audit must be performed in accordance with the requirements of U.S. Government Accountability Office’s (GAO) Government Auditing Standards, located at Yellow Book | U.S. GAO, and the requirements of Subpart F of 2 C.F.R. Part 200, located at eCFR :: 2 CFR Part 200 Subpart F -- Audit Requirements.

5.   Monitoring and Oversight

Per 2 C.F.R. § 200.337, FEMA, through its authorized representatives, has the right, at all reasonable times, to make site visits or conduct desk reviews to review project accomplishments and management control systems to review award progress and to provide any required technical assistance. During site visits or desk reviews, FEMA will review recipients’ files related to the award. As part of any monitoring and program evaluation activities, recipients must permit FEMA, upon reasonable notice, to review grant-related records and to interview the organization’s staff and contractors regarding the program. Recipients must respond in a timely and accurate manner to FEMA requests for information relating to the award.

Effective monitoring and oversight help FEMA ensure that recipients use grant funds for their intended purpose(s); verify that projects undertaken are consistent with approved plans; and ensure that recipients make adequate progress toward stated goals and objectives. Additionally, monitoring serves as the primary mechanism to ensure that recipients comply with applicable laws, rules, regulations, program guidance, and requirements. FEMA regularly monitors all grant programs both financially and programmatically in accordance with federal laws, regulations (including 2 C.F.R. Part 200), program guidance, and the terms and conditions of the award. All monitoring efforts ultimately serve to evaluate progress towards grant goals and proactively target and address issues that may threaten grant success during the period of performance.

FEMA staff will periodically monitor recipients to ensure that administrative processes, policies and procedures, budgets, and other related award criteria are meeting Federal Government-wide and FEMA regulations. Aside from reviewing quarterly financial and programmatic reports, FEMA may also conduct enhanced monitoring through either desk-based reviews, onsite monitoring visits, or both. Enhanced monitoring will involve the review and analysis of the financial compliance and administrative processes, policies, activities, and other attributes of each federal assistance award, and it will identify areas where the recipient may need technical assistance, corrective actions, or other support.

Financial and programmatic monitoring are complementary processes within FEMA’s overarching monitoring strategy that function together to ensure effective grants management, accountability, and transparency; validate progress against grant and program goals; and safeguard federal funds against fraud, waste, and abuse. Financial monitoring primarily focuses on statutory and regulatory compliance with administrative grant requirements, while programmatic monitoring seeks to validate and assist in grant progress, targeting issues that may be hindering achievement of project goals and ensuring compliance with the purpose of the grant and grant program. Both monitoring processes are similar in that they feature initial reviews of all open awards, and additional, in-depth monitoring of grants requiring additional attention.

Recipients and subrecipients who are pass-through entities are responsible for monitoring their subrecipients in a manner consistent with the terms of the federal award at 2 C.F.R. Part 200, including 2 C.F.R. § 200.332. This includes the pass-through entity’s responsibility to monitor the activities of the subrecipient as necessary to ensure that the subaward is used for authorized purposes, in compliance with federal statutes, regulations, and the terms and conditions of the subaward; and that subaward performance goals are achieved.

In terms of overall award management, recipient and subrecipient responsibilities include, but are not limited to: accounting of receipts and expenditures, cash management, maintaining adequate financial records, reporting and refunding expenditures disallowed by audits, monitoring if acting as a pass-through entity, or other assessments and reviews, and ensuring overall compliance with the terms and conditions of the award or subaward, as applicable, including the terms of 2 C.F.R. Part 200.

G.  DHS Awarding Agency Contact Information

1.   Contact and Resource Information

a.   Program Office Contact

FEMA has region-specific Preparedness Officers. If you do not know your Preparedness Officer, please contact the FEMA Grants Information Desk by e-mail at fema-grants-news@fema.dhs.gov OR by phone at (800) 368-6498, Monday through Friday, 9 a.m. – 5 p.m. ET.

b.   FEMA Grants News

FEMA Grants News is a non-emergency comprehensive management and information resource developed by FEMA for grants stakeholders. This channel provides general information on all FEMA grant programs and maintains a comprehensive database containing key personnel contact information at the federal, state, and local levels. When necessary, recipients will be directed to a federal point of contact who can answer specific programmatic questions or concerns. FEMA Grants Information Desk can be reached by e-mail at fema-grants-news@fema.dhs.gov OR by phone at (800) 368-6498, Monday through Friday, 9 a.m. – 5 p.m. ET.

c.   Grant Programs Directorate (GPD) Award Administration Division

GPD’s Award Administration Division (AAD) provides support regarding financial matters and budgetary technical assistance. Additional guidance and information can be obtained by contacting the AAD’s Help Desk via e-mail at ASK-GMD@fema.dhs.gov.

d.   FEMA Regional Offices

FEMA Regional Offices manage, administer, and conduct the application budget review, create the award package, approve, amend, and close out awards, as well as conduct cash analysis, financial and programmatic monitoring, and audit resolution for the EOC Grant Program. The Regions also provide technical assistance to EOC Grant Program recipients.

FEMA Regional Office contact information is available at Regions, States and Territories | FEMA.gov.

e.   Equal Rights

The FEMA Office of Equal Rights (OER) is responsible for compliance with and enforcement of federal civil rights obligations in connection with programs and services conducted by FEMA and recipients of FEMA financial assistance. All inquiries and communications about federal civil rights compliance for FEMA grants under this NOFO should be sent to FEMA-CivilRightsOffice@fema.dhs.gov.

f.    Environmental Planning and Historic Preservation

GPD’s EHP Team provides guidance and information about the EHP review process to recipients and subrecipients. All inquiries and communications about GPD projects under this NOFO or the EHP review process, including the submittal of EHP review materials, should be sent to gpdehpinfo@fema.dhs.gov.

2.   Systems Information

a.   Grants.gov

For technical assistance with Grants.gov, call the customer support hotline 24 hours per day, 7 days per week (except federal holidays) at (800) 518-4726 or e-mail at support@grants.gov.

b.   Non-Disaster (ND) Grants

For technical assistance with the ND Grants system, please contact the ND Grants Helpdesk at ndgrants@fema.dhs.gov or (800) 865-4076, Monday through Friday, 9:00 AM – 6:00 PM ET. User resources are available at Non-Disaster Grants Management System | FEMA.gov.

c.   Payment and Reporting System (PARS)

FEMA uses the Payment and Reporting System (PARS) for financial reporting, invoicing, and tracking payments. FEMA uses the Direct Deposit/Electronic Funds Transfer (DD/EFT) method of payment to recipients. For questions about the online system, please call the Customer Service Center at (866) 927-5646 or email ask-GMD@fema.dhs.gov.

H.  Additional Information

1.   Termination Provisions

FEMA may terminate a federal award in whole or in part for one of the following reasons. FEMA and the recipient must still comply with closeout requirements at 2 C.F.R. §§ 200.344-200.345 even if an award is terminated in whole or in part. To the extent that subawards are permitted under this NOFO, pass-through entities should refer to 2 C.F.R. § 200.340 for additional information on termination regarding subawards.

a.   Noncompliance

If a recipient fails to comply with the terms and conditions of a federal award, FEMA may terminate the award in whole or in part. If the noncompliance can be corrected, FEMA may first attempt to direct the recipient to correct the noncompliance. This may take the form of a Compliance Notification. If the noncompliance cannot be corrected or the recipient is non-responsive, FEMA may proceed with a Remedy Notification, which could impose a remedy for noncompliance per 2 C.F.R. § 200.339, including termination. Any action to terminate based on noncompliance will follow the requirements of 2 C.F.R. §§ 200.341-200.342 as well as the requirement of 2 C.F.R. § 200.340(c) to report in FAPIIS the recipient’s material failure to comply with the award terms and conditions. See also the section on Actions to Address Noncompliance in this NOFO.

b.   With the Consent of the Recipient

FEMA may also terminate an award in whole or in part with the consent of the recipient, in which case the parties must agree upon the termination conditions, including the effective date, and in the case of partial termination, the portion to be terminated.

c.   Notification by the Recipient

The recipient may terminate the award, in whole or in part, by sending written notification to FEMA setting forth the reasons for such termination, the effective date, and in the case of partial termination, the portion to be terminated. In the case of partial termination, FEMA may determine that a partially terminated award will not accomplish the purpose of the federal award, so FEMA may terminate the award in its entirety. If that occurs, FEMA will follow the requirements of 2 C.F.R. §§ 200.341-200.342 in deciding to fully terminate the award.

2.  Program Evaluation

Recipients and subrecipients are encouraged to incorporate program evaluation activities from the outset of their program design and implementation to meaningfully document and measure their progress towards meeting an agency priority goal(s). Title I of the Foundations for Evidence-Based Policymaking Act of 2018 (Evidence Act), Pub. L. No. 115-435 (2019) urges federal awarding agencies and federal assistance recipients and subrecipients to use program evaluation as a critical tool to learn, to improve equitable delivery, and to elevate program service and delivery across the program lifecycle. Evaluation means “an assessment using systematic data collection and analysis of one or more programs, policies, and organizations intended to assess their effectiveness and efficiency.” Evidence Act § 101 (codified at 5 U.S.C. § 311). Evaluation costs are allowable costs (either as direct or indirect), unless prohibited by statute or regulation.

In addition, recipients are required to participate in a DHS-led evaluation if selected, which may be carried out by a third-party on behalf of the Program Office or DHS. By accepting grant funds, recipients agree to participate in the evaluation, which may include analysis of individuals who benefit from the grant, and provide access to program operating personnel and participants, as specified by the evaluator(s) during the award.

3.   Period of Performance Extensions

Extensions to the period of performance for this program are allowed. Extensions to the POP identified in the award will only be considered through formal, written requests to the recipient’s FEMA Preparedness Officer and must contain specific and compelling justifications as to why an extension is required. Recipients are advised to coordinate with the FEMA Preparedness Officer as needed when preparing an extension request.

All extension requests must address the following:

  1. The grant program, fiscal year, and award number;
  2. Reason for the delay –including details of the legal, policy, or operational challenges that prevent the final outlay of awarded funds by the deadline;
  3. Current status of the activity(ies);
  4. Approved POP termination date and new project completion date;
  5. Amount of funds drawn down to date;
  6. Remaining available funds, both federal and, if applicable, non-federal;
  7.  Budget outlining how remaining federal and, if applicable, non-federal funds will be expended;
  8. Plan for completion, including milestones and timeframes for achieving each milestone and the position or person responsible for implementing the plan for completion; and
  9. Certification that the activity(ies) will be completed within the extended POP without any modification to the original statement of work, as described in the Investment Justification and as approved by FEMA.

Extension requests will be granted only due to compelling legal, policy, or operational challenges. Extension requests will only be considered for the following reasons:

  • ·Contractual commitments by the recipient or subrecipient with vendors prevent completion of the project, including delivery of equipment or services, within the existing POP;
  •  The project must undergo a complex environmental review that cannot be completed within the existing POP;
  • ·Projects are long-term by design, and therefore acceleration would compromise core programmatic goals; or
  • Where other special or extenuating circumstances exist.

Recipients should submit all proposed extension requests to FEMA for review and approval at least 120 days prior to the end of the POP to allow sufficient processing time. Extensions are typically granted for no more than a six-month period.

4.   Disability Integration

Pursuant to Section 504 of the Rehabilitation Act of 1973, recipients of FEMA financial assistance must ensure that their programs and activities do not discriminate against other qualified individuals with disabilities.

Grant recipients should engage with the whole community to advance individual and community preparedness and to work as a nation to build and sustain resilience. In doing so, recipients are encouraged to consider the needs of individuals with disabilities into the activities and projects funded by the grant.

FEMA expects that the integration of the needs of people with disabilities will occur at all levels, including planning; alerting, notification, and public outreach; training; purchasing of equipment and supplies; protective action implementation; and exercises/drills.

The following are examples that demonstrate the integration of the needs of people with disabilities in carrying out FEMA awards:

FEMA grant recipients can fund projects towards the resiliency of the whole community, including people with disabilities, such as training, outreach and safety campaigns, provided that the project aligns with this NOFO and the terms and conditions of the award.

5.   Conflicts of Interest in the Administration of Federal Awards or Subawards

For conflicts of interest under grant-funded procurements and contracts, refer to the section on Procurement Integrity in this NOFO and 2 C.F.R. §§ 200.317 – 200.327.

To eliminate and reduce the impact of conflicts of interest in the subaward process, recipients and pass-through entities must follow their own policies and procedures regarding the elimination or reduction of conflicts of interest when making subawards. Recipients and pass-through entities are also required to follow any applicable federal and state, local, tribal, or territorial (SLTT) statutes or regulations governing conflicts of interest in the making of subawards.

The recipient or pass-through entity must disclose to the respective Regional EOC  Program Manager, in writing, any real or potential conflict of interest that may arise during the administration of the federal award, as defined by the federal or SLTT statutes or regulations or their own existing policies, within five days of learning of the conflict of interest. Similarly, subrecipients, whether acting as subrecipients or as pass-through entities, must disclose any real or potential conflict of interest to the recipient or next-level pass-through entity as required by the recipient or pass-through entity’s conflict of interest policies, or any applicable federal or SLTT statutes or regulations.

Conflicts of interest may arise during the process of FEMA making a federal award in situations where an employee, officer, or agent, any members of their immediate family and/or their partner has a close personal relationship, a business relationship, or a professional relationship, with an applicant, subapplicant, recipient, subrecipient, or FEMA employees.

6.   Procurement Integrity

Through audits conducted by the DHS Office of Inspector General (OIG) and FEMA grant monitoring, findings have shown that some FEMA recipients have not fully adhered to the proper procurement requirements at 2 C.F.R. §§ 200.317 – 200.327 when spending grant funds. Anything less than full compliance with federal procurement requirements jeopardizes the integrity of the grant as well as the grant program. To assist with determining whether an action is a procurement or instead a subaward, please consult 2 C.F.R. § 200.331. For detailed guidance on the federal procurement standards, recipients and subrecipients should refer to various materials issued by FEMA’s Procurement Disaster Assistance Team (PDAT), such as the PDAT Field Manual and Contract Provisions Guide. Additional resources, including an upcoming trainings schedule can be found on the PDAT Website: Contracting with Federal Funds for Goods and Services Before, During and After Disasters | FEMA.gov.

The below highlights the federal procurement requirements for FEMA recipients when procuring goods and services with federal grant funds. FEMA will include a review of recipients’ procurement practices as part of the normal monitoring activities. All procurement activity must be conducted in accordance with federal procurement standards at 2 C.F.R. §§ 200.317 – 200.327. Select requirements under these standards are listed below. The recipient and any of its subrecipients must comply with all requirements, even if they are not listed below.

Under 2 C.F.R. § 200.317, when procuring property and services under a federal award, states (including territories) must follow the same policies and procedures they use for procurements from their non-federal funds; additionally, states must now follow 2 C.F.R. § 200.321 regarding socioeconomic steps, 200.322 regarding domestic preferences for procurements, 200.323 regarding procurement of recovered materials, and 2 C.F.R. § 200.327 regarding required contract provisions.

All other non-federal entities, such as tribes (collectively, non-state entities), must have and use their own documented procurement procedures that reflect applicable SLTT laws and regulations, provided that the procurements conform to applicable federal law and the standards identified in 2 C.F.R. Part 200. These standards include, but are not limited to, providing for full and open competition consistent with the standards of 2 C.F.R. § 200.319 and the required procurement methods at § 200.320.

a.   Important Changes to Procurement Standards in 2 C.F.R. Part 200

OMB recently updated various parts of Title 2 of the Code of Federal Regulations, among them, the procurement standards. States are now required to follow the socioeconomic steps in soliciting small and minority businesses, women’s business enterprises, and labor surplus area firms per 2 C.F.R. § 200.321. All non-federal entities should also, to the greatest extent practicable under a federal award, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States per 2 C.F.R. § 200.322. More information on OMB’s revisions to the federal procurement standards can be found in Purchasing Under a FEMA Award: OMB Revisions Fact Sheet.

The recognized procurement methods in 2 C.F.R. § 200.320 have been reorganized into informal procurement methods, which include micro-purchases and small purchases; formal procurement methods, which include sealed bidding and competitive proposals; and noncompetitive procurements. The federal micro-purchase threshold is currently $10,000, and non-state entities may use a lower threshold when using micro-purchase procedures under a FEMA award. If a non-state entity wants to use a micro-purchase threshold higher than the federal threshold, it must follow the requirements of 2 C.F.R. § 200.320(a)(1)(iii)-(v). The federal simplified acquisition threshold is currently $250,000, and a non-state entity may use a lower threshold but may not exceed the federal threshold when using small purchase procedures under a FEMA award. See 2 C.F.R. § 200.1 (citing the definition of simplified acquisition threshold from 48 C.F.R. Part 2, Subpart 2.1).

See 2 C.F.R. §§ 200.216, 200.471, and Appendix II as well as section D.13.a of the NOFO regarding prohibitions on covered telecommunications equipment or services.

b.   Competition and Conflicts of Interest

Among the requirements of 2 C.F.R. § 200.319(b) applicable to all non-federal entities other than states, in order to ensure objective contractor performance and eliminate unfair competitive advantage, contractors that develop or draft specifications, requirements, statements of work, or invitations for bids or requests for proposals must be excluded from competing for such procurements. FEMA considers these actions to be an organizational conflict of interest and interprets this restriction as applying to contractors that help a non-federal entity develop its grant application, project plans, or project budget. This prohibition also applies to the use of former employees to manage the grant or carry out a contract when those former employees worked on such activities while they were employees of the non-federal entity.

Under this prohibition, unless the non-federal entity solicits for and awards a contract covering both development and execution of specifications (or similar elements as described above), and this contract was procured in compliance with 2 C.F.R. §§ 200.317 – 200.327, federal funds cannot be used to pay a contractor to carry out the work if that contractor also worked on the development of those specifications. This rule applies to all contracts funded with federal grant funds, including pre-award costs, such as grant writer fees, as well as post-award costs, such as grant management fees.

Additionally, some of the situations considered to be restrictive of competition include, but are not limited to:

  • Placing unreasonable requirements on firms for them to qualify to do business;
  • Requiring unnecessary experience and excessive bonding;
  • Noncompetitive pricing practices between firms or between affiliated companies;
  • Noncompetitive contracts to consultants that are on retainer contracts;
  •  Organizational conflicts of interest;
  • Specifying only a “brand name” product instead of allowing “an equal” product to be offered and describing the performance or other relevant requirements of the procurement; and
  • Any arbitrary action in the procurement process.

Per 2 C.F.R. § 200.319(c), non-federal entities other than states must conduct procurements in a manner that prohibits the use of statutorily or administratively imposed SLTT geographical preferences in the evaluation of bids or proposals, except in those cases where applicable federal statutes expressly mandate or encourage geographic preference. Nothing in this section preempts state licensing laws. When contracting for architectural and engineering services, geographic location may be a selection criterion provided its application leaves an appropriate number of qualified firms, given the nature and size of the project, to compete for the contract.

Under 2 C.F.R. § 200.318(c)(1), non-federal entities other than states are required to maintain written standards of conduct covering conflicts of interest and governing the actions of their employees engaged in the selection, award, and administration of contracts. No employee, officer, or agent may participate in the selection, award, or administration of a contract supported by a federal award if he or she has a real or apparent conflict of interest. Such conflicts of interest would arise when the employee, officer or agent, any member of their immediate family, their partner, or an organization that employs or is about to employ any of the parties indicated herein, has a financial or other interest in or a tangible personal benefit from a firm considered for a contract. The officers, employees, and agents of the non-federal entity may neither solicit nor accept gratuities, favors, or anything of monetary value from contractors or parties to subcontracts. However, non-federal entities may set standards for situations in which the financial interest is not substantial, or the gift is an unsolicited item of nominal value. The standards of conduct must provide for disciplinary actions to be applied for violations of such standards by officers, employees, or agents of the non-federal entity.

Under 2 C.F.R. 200.318(c)(2), if the recipient or subrecipient (other than states) has a parent, affiliate, or subsidiary organization that is not a state, local, tribal, or territorial government, the non-federal entity must also maintain written standards of conduct covering organizational conflicts of interest. In this context, organizational conflict of interest means that because of a relationship with a parent company, affiliate, or subsidiary organization, the non-federal entity is unable or appears to be unable to be impartial in conducting a procurement action involving a related organization. The non-federal entity must disclose in writing any potential conflicts of interest to FEMA or the pass-through entity in accordance with applicable FEMA policy.

c.   Supply Schedules and Purchasing Programs

Generally, a non-federal entity may seek to procure goods or services from a federal supply schedule, state supply schedule, or group purchasing agreement.

i.    General Services Administration Schedules

States, tribes, and local governments, and any instrumentality thereof (such as local education agencies or institutions of higher education) may procure goods and services from a General Services Administration (GSA) schedule. GSA offers multiple efficient and effective procurement programs for state, tribal, and local governments, and instrumentalities thereof, to purchase products and services directly from pre-vetted contractors. The GSA Schedules (also referred to as the Multiple Award Schedules and the Federal Supply Schedules) are long-term government-wide contracts with commercial firms that provide access to millions of commercial products and services at volume discount pricing.

Information about GSA programs for states, tribes, and local governments, and instrumentalities thereof, can be found at Programs for State and Local Governments | GSA and State and Local Governments | GSA.

For tribes, local governments, and their instrumentalities that purchase off of a GSA schedule, this will satisfy the federal requirements for full and open competition provided that the recipient follows the GSA ordering procedures; however, tribes, local governments, and their instrumentalities will still need to follow the other rules under 2 C.F.R. §§ 200.317 – 200.327, such as solicitation of minority businesses, women’s business enterprises, small businesses, or labor surplus area firms (§ 200.321), domestic preferences (§ 200.322), contract cost and price (§ 200.324), and required contract provisions (§ 200.327 and Appendix II).

ii.   Other Supply Schedules and Programs

For non-federal entities other than states, such as tribes, local governments, and nonprofits, that want to procure goods or services from a state supply schedule, cooperative purchasing program, or other similar program, in order for such procurements to be permissible under federal requirements, the following must be true:

  • The procurement of the original contract or purchasing schedule and its use by the non-federal entity complies with state and local law, regulations, and written procurement procedures.
  • The state or other entity that originally procured the original contract or purchasing schedule entered into the contract or schedule with the express purpose of making it available to the non-federal entity and other similar types of entities.
  • The contract or purchasing schedule specifically allows for such use, and the work to be performed for the non-federal entity falls within the scope of work under the contract as to type, amount, and geography.
  • · The procurement of the original contract or purchasing schedule complied with all the procurement standards applicable to a non-federal entity other than states under at 2 C.F.R. §§ 200.317 – 200.327.
  • With respect to the use of a purchasing schedule, the non-federal entity must follow ordering procedures that adhere to applicable state, tribal, and local laws and regulations and the minimum requirements of full and open competition under 2 C.F.R. Part 200.

If a non-federal entity other than a state seeks to use a state supply schedule, cooperative purchasing program, or other similar type of arrangement, FEMA recommends the recipient discuss the procurement plans with its FEMA Preparedness Officer.

d.   Procurement Documentation

Per 2 C.F.R. § 200.318(i), non-federal entities other than states and territories are required to maintain and retain records sufficient to detail the history of procurement covering at least the rationale for the procurement method, selection of contract type, contractor selection or rejection, and the basis for the contract price. States and territories are encouraged to maintain and retain this information as well and are reminded that in order for any cost to be allowable, it must be adequately documented per 2 C.F.R. § 200.403(g).

Examples of the types of documents that would cover this information include but are not limited to:

  • ·Solicitation documentation, such as requests for quotes, invitations for bids, or requests for proposals;
  • ·Responses to solicitations, such as quotes, bids, or proposals;
  • Pre-solicitation independent cost estimates and post-solicitation cost/price analyses on file for review by federal personnel, if applicable;
  • Contract documents and amendments, including required contract provisions; and
  •  Other documents required by federal regulations applicable at the time a grant is awarded to a recipient.

Additional information on required procurement records can be found on pages 24-26 of the PDAT Field Manual.

7.   Financial Assistance Programs for Infrastructure

a.   Build America, Buy America Act

Recipients and subrecipients must comply with the Build America, Buy America Act (BABAA), which was enacted as part of the Infrastructure Investment and Jobs Act §§ 70901-70927, Pub. L. No. 117-58 (2021); and Executive Order 14005, Ensuring the Future is Made in All of America by All of America’s Workers. See also OMB Memorandum M-22-11, Initial Implementation Guidance on Application of Buy America Preference in Federal Financial Assistance Programs for Infrastructure.

None of the funds provided under this program may be used for a project for infrastructure unless the iron and steel, manufactured products, and construction materials used in that infrastructure are produced in the United States.

The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.

To see whether a particular FEMA federal financial assistance program is considered an infrastructure program and thus required to include a Buy America preference, please see Programs and Definitions: Build America, Buy America Act | FEMA.gov and Build America, Buy America Act Frequently Asked Questions (FAQs) | FEMA.gov. Additional information is found in Buy America Preference in FEMA Financial Assistance Programs for Infrastructure, FEMA Interim Policy #207-22-0001.

b.   Waivers

When necessary, recipients (and subrecipients through their pass-through entity) may apply for, and FEMA may grant, a waiver from these requirements.

A waiver of the domestic content procurement preference may be granted by the agency awarding official if FEMA determines that:

  • Applying the domestic content procurement preference would be inconsistent with the public interest.
  • The types of iron, steel, manufactured products, or construction materials are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality.
  • The inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the overall project by more than 25%.

For FEMA awards, the process for requesting a waiver from the Buy America preference requirements can be found on FEMA’s website at: "Buy America" Preference in FEMA Financial Assistance Programs for Infrastructure | FEMA.gov.

C. Definitions

Construction materials: an article, material, or supply—other than an item primarily of iron or steel; a manufactured product; cement and cementitious materials; aggregates such as stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of non-ferrous metals, plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables), glass (including optic glass), lumber, paint, and drywall.

Domestic content procurement preference: Means all iron and steel used in the project are produced in the United States; the manufactured products used in the project are produced in the United States; or the construction materials used in the project are produced in the United States.

Federal financial assistance: Generally defined in 2 C.F.R. § 200.1 and includes all expenditures by a federal agency to a non-federal entity for an infrastructure project, except that it does not include expenditures for assistance authorities relating to major disasters or emergencies under sections 402, 403, 404, 406, 408, or 502 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act relating to a major disaster or emergency declared under section 401 or 501, respectively, or pre and post disaster or emergency response expenditures.

Infrastructure:  infrastructure projects which serve a public function, including at a minimum, the structures, facilities, and equipment for, in the United States, roads, highways, and bridges; public transportation; dams, ports, harbors, and other maritime facilities; intercity passenger and freight railroads; freight and intermodal facilities; airports; water systems, including drinking water and wastewater systems; electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property; and structures, facilities, and equipment that generate, transport, and distribute energy.

Produced in the United States means the following for:

  • Iron and steel: All manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.
  • Manufactured products: The product was manufactured in the United States, and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55% of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation.
  • Construction Materials: All manufacturing processes for the construction material occurred in the United States.

Project: is any activity related to the construction, alteration, maintenance, or repair of infrastructure in the United States.

8.   Record Retention

a.   Record Retention Period

Financial records, supporting documents, statistical records, and all other non-Federal entity records pertinent to a Federal award generally must be maintained for at least three years from the date the final FFR is submitted. See 2 C.F.R. § 200.334. Further, if the recipient does not submit a final FFR and the award is administratively closed, FEMA uses the date of administrative closeout as the start of the general record retention period.

The record retention period may be longer than three years or have a different start date in certain cases. These include:

  •  Records for real property and equipment acquired with Federal funds must be retained for three years after final disposition of the property. See 2 C.F.R. § 200.334(c).
  • · If any litigation, claim, or audit is started before the expiration of the three-year period, the records must be retained until all litigation, claims, or audit findings involving the records have been resolved and final action taken. See 2 C.F.R. § 200.334(a).
  •  The record retention period will be extended if the non-federal entity is notified in writing of the extension by FEMA, the cognizant or oversight agency for audit, or the cognizant agency for indirect costs, or pass-through entity. See 2 C.F.R. § 200.334(b).
  • Where FEMA requires recipients to report program income after the period of performance ends, the program income record retention period begins at the end of the recipient’s fiscal year in which program income is earned. See 2 C.F.R. § 200.334(e).
  • · For indirect cost rate computations and proposals, cost allocation plans, or any similar accounting computations of the rate at which a particular group of costs is chargeable (such as computer usage chargeback rates or composite fringe benefit rates), the start of the record retention period depends on whether the indirect cost rate documents were submitted for negotiation. If the indirect cost rate documents were submitted for negotiation, the record retention period begins from the date those documents were submitted for negotiation. If indirect cost rate documents were not submitted for negotiation, the record retention period begins at the end of the recipient’s fiscal year or other accounting period covered by that indirect cost rate. See 2 C.F.R. § 200.334(f).

b.   Types of Records to Retain

FEMA requires that non-federal entities maintain the following documentation for federally funded purchases:

  • · Specifications;
  • · Solicitations;
  • · Competitive quotes or proposals;
  • · Basis for selection decisions;
  • · Purchase orders;
  • · Contracts;
  • · Invoices; and
  • · Canceled checks.

Non-federal entities should keep detailed records of all transactions involving the grant. FEMA may at any time request copies of any relevant documentation and records, including purchasing documentation along with copies of cancelled checks for verification. See, e.g., 2 C.F.R. §§ 200.318(i), 200.334, 200.337.

In order for any cost to be allowable, it must be adequately documented per 2 C.F.R. § 200.403(g). Non-federal entities who fail to fully document all purchases may find their expenditures questioned and subsequently disallowed

9.   Actions to Address Noncompliance

Non-federal entities receiving financial assistance funding from FEMA are required to comply with requirements in the terms and conditions of their awards or subawards, including the terms set forth in applicable federal statutes, regulations, NOFOs, and policies. Throughout the award lifecycle or even after an award has been closed, FEMA or the pass-through entity may discover potential or actual noncompliance on the part of a recipient or subrecipient. This potential or actual noncompliance may be discovered through routine monitoring, audits, closeout, or reporting from various sources.

In the case of any potential or actual noncompliance, FEMA may place special conditions on an award per 2 C.F.R. §§ 200.208 and 200.339, FEMA may place a hold on funds until the matter is corrected, or additional information is provided per 2 C.F.R. § 200.339, or it may do both. Similar remedies for noncompliance with certain federal civil rights laws are authorized pursuant to 44 C.F.R. Parts 7 and 19.

In the event the noncompliance is not able to be corrected by imposing additional conditions or the recipient or subrecipient refuses to correct the matter, FEMA might take other remedies allowed under 2 C.F.R. § 200.339. These remedies include actions to disallow costs, recover funds, wholly or partly suspend or terminate the award, initiate suspension and debarment proceedings, withhold further federal awards, or take other remedies that may be legally available. For further information on termination due to noncompliance, see the section on Termination Provisions in the NOFO.

FEMA may discover and take action on noncompliance even after an award has been closed. The closeout of an award does not affect FEMA’s right to disallow costs and recover funds as long the action to disallow costs takes place during the record retention period. See 2 C.F.R. §§ 200.334, 200.345(a). Closeout also does not affect the obligation of the non-federal entity to return any funds due as a result of later refunds, corrections, or other transactions. 2 C.F.R. § 200.345(a)(2).

The types of funds FEMA might attempt to recover include, but are not limited to, improper payments, cost share reimbursements, program income, interest earned on advance payments, or equipment disposition amounts.

FEMA may seek to recover disallowed costs through a Notice of Potential Debt Letter, a Remedy Notification, or other letter. The document will describe the potential amount owed, the reason why FEMA is recovering the funds, the recipient’s appeal rights, how the amount can be paid, and the consequences for not appealing or paying the amount by the deadline.

If the recipient neither appeals nor pays the amount by the deadline, the amount owed will become final. Potential consequences if the debt is not paid in full or otherwise resolved by the deadline include the assessment of interest, administrative fees, and penalty charges; administratively offsetting the debt against other payable federal funds; and transferring the debt to the U.S. Department of the Treasury for collection.

FEMA notes the following common areas of noncompliance for FEMA’s grant programs:

  • Insufficient documentation and lack of record retention;
  • Failure to follow the procurement under grants requirements;
  • Failure to submit closeout documents in a timely manner;
  • Failure to follow EHP requirements; and
  • Failure to comply with the POP deadline.

10. Audits

 

DHS OIG, the GAO, the pass-through entity, or independent auditing firms for single audits, and may cover activities and costs incurred under the award. Auditing agencies such as the DHS OIG, the GAO, and the pass-through entity (if applicable), and FEMA in its oversight capacity, must have access to records pertaining to the FEMA award. Recipients and subrecipients must retain award documents for at least three years from the date the final FFR is submitted, and even longer in many cases subject to the requirements of 2 C.F.R. § 200.334. In the case of administrative closeout, documents must be retained for at least three years from the date of closeout, or longer subject to the requirements of 2 C.F.R. § 200.334. If documents are retained longer than the required retention period, the DHS OIG, the GAO, and the pass-through entity, as well as FEMA in its oversight capacity, have the right to access these records as well. See 2 C.F.R. §§ 200.334, 200.337.

Additionally, non-federal entities must comply with the single audit requirements at 2 C.F.R. Part 200, Subpart F. Specifically, non-federal entities, other than for-profit subrecipients, that expend $750,000 or more in federal awards during their fiscal year must have a single or program-specific audit conducted for that year in accordance with Subpart F. 2 C.F.R. § 200.501. A single audit covers all federal funds expended during a fiscal year, not just FEMA funds. The cost of audit services may be allowable per 2 C.F.R. § 200.425, but non-federal entities must select auditors in accordance with 2 C.F.R. § 200.509, including following the proper procurement procedures. For additional information on single audit reporting requirements, see Section F.4.e of this NOFO.

The objectives of single audits are to:

  • Determine if financial statements conform to generally accepted accounting principles (GAAP);
  • Determine whether the schedule of expenditures of federal awards is presented fairly;
  •  Understand, assess, and test the adequacy of internal controls for compliance with major programs; and
  • ·Determine if the entity complied with applicable laws, regulations, and contracts or grants.

For single audits, the auditee is required to prepare financial statements reflecting its financial position, a schedule of federal award expenditures, and a summary of the status of prior audit findings and questioned costs. The auditee also is required to follow up and take appropriate corrective actions on new and previously issued but not yet addressed audit findings. The auditee must prepare a corrective action plan to address the new audit findings. 2 C.F.R. §§ 200.508, 200.510, 200.511.

Non-federal entities must have an audit conducted, either single or program-specific, of their financial statements and federal expenditures annually or biennially pursuant to 2 C.F.R. § 200.504. Non-federal entities must also follow the information submission requirements of 2 C.F.R. § 200.512, including submitting the audit information to the Federal Audit Clearinghouse within the earlier of 30 calendar days after receipt of the auditor’s report(s) or nine months after the end of the audit period. The audit information to be submitted include the data collection form described at 2 C.F.R. § 200.512(c) and Appendix X to 2 C.F.R. Part 200 as well as the reporting package described at 2 C.F.R. § 200.512(b).

The non-federal entity must retain one copy of the data collection form and one copy of the reporting package for three years from the date of submission to the Federal Audit Clearinghouse. 2 C.F.R. § 200.512; see also 2 C.F.R. § 200.517 (setting requirements for retention of documents by the auditor and access to audit records in the auditor’s possession).

FEMA, the DHS OIG, the GAO, and the pass-through entity (if applicable), as part of monitoring or as part of an audit, may review a non-federal entity’s compliance with the single audit requirements. In cases of continued inability or unwillingness to have an audit conducted in compliance with 2 C.F.R. Part 200, Subpart F, FEMA and the pass-through entity, if applicable, are required to take appropriate remedial action under 2 C.F.R. § 200.339 for noncompliance, pursuant to 2 C.F.R. § 200.505.

11. Payment Information

FEMA uses the Direct Deposit/Electronic Funds Transfer (DD/EFT) method of payment to recipients.

FEMA utilizes the Payment and Reporting System (PARS) for financial reporting, invoicing, and tracking payments. For additional information, refer to PARS Security (fema.gov).

12. Procedures for Establishing Indirect Cost Rates

The requirements and procedures for establishing indirect cost rates are the same for all the preparedness programs outlined in the FY 2023 Preparedness Grants Manual. The process for establishing the indirect cost rate varies based on the type of entity and the amount of funding they receive:

  • If the entity is a non-governmental entity, and is a subrecipient, indirect cost rate procedures are outlined in 2 CFR 200.332(a)(4). These types of entities may either use the de minimis rate or negotiate a rate with the pass-through entity.
  • If the subrecipient is a state or local governmental entity, indirect cost rate procedures are established in 2 CFR 200, Appendix VII.
    • Per Paragraph D.1.b. of Appendix VII, state or local governmental entities receiving grant funds must develop an indirect cost rate proposal.
    • If the state or local entity receives more than $35 million in grant funding, the proposal must be approved by the cognizant agency.
    • If a state or local entity receives $35 million or less in grant funding, they have to develop an indirect cost rate proposal, but that indirect cost rate proposal does not need to be approved by the cognizant agency.
  • If a state or local governmental entity wants to use the de minimis rate (instead of developing an indirect cost rate proposal), they can request a case-by-case exception from FEMA (per 2 CFR 200.102(b)).

13. Whole Community Preparedness

Preparedness is a shared responsibility that calls for the involvement of everyone—not just the government—in preparedness efforts. By working together, everyone can help keep the nation safe from harm and help keep it resilient when struck by hazards, such as natural disasters, acts of terrorism, and pandemics.

Whole Community includes:

  • Individuals and families, including those with access and functional needs;
  • Businesses;
  • Faith-based and community organizations;
  • Nonprofit groups;
  • Schools and academia;
  •  Media outlets; and
  • All levels of government, including state, local, tribal, territorial, and federal partners.

The phrase “Whole Community” often appears in preparedness materials, as it is one of the guiding principles. It means two things:

  1. Involving people in the development of national preparedness documents; and
  2. Ensuring their roles and responsibilities are reflected in the content of the materials.

Appendix A – FY 2023 EOC Grant Program Project List

Download the project list.

 

Tags:
Last updated