EHP and Other Compliance

Appeal Brief Appeal Letter Appeal Analysis

Appeal Brief

Disaster4399
ApplicantFlorida Department of Environmental Protection
Appeal TypeSecond
PA ID#000-U03AE-00
PW ID#GMP 133304/PW 1897
Date Signed2024-08-19T16:00:00

Summary Paragraph

Hurricane Michael caused extensive damage throughout Florida, resulting in a major disaster declaration on October 11, 2018. The Florida Department of Environmental Protection (Applicant) requested Public Assistance (PA) for multiple disaster-damaged buildings at T.H. Stone Memorial St. Joseph Peninsula State Park. FEMA created Grants Manager Project 133304 to document damages totaling $1,061,712.46 for multiple buildings, including the Park Managers Residence and Storage, and Assistant Park Manager Residence and Storage buildings. FEMA issued multiple requests for information, seeking information including the percentage of work performed and specific building locations. The Applicant responded, providing the requested information, including scope of work documentation. FEMA issued a Determination Memorandum denying $882,335.88, finding the Applicant conducted construction work prior to FEMA’s required federal Environmental and Historic Preservation (EHP) review, and the new constructions were in floodplain areas. The Applicant appealed, stating that it provided FEMA the new construction locations, FEMA requested no additional information, and that the relocated buildings were within the same flood zones. FEMA denied the appeal, finding the Applicant did not provide documentation verifying the work complied with applicable EHP requirements. The Applicant submits a second appeal, stating that the new locations of the buildings were discussed with local flood agencies.

Authorities

  • Stafford Act § 406.
  • 44 C.F.R. §§ 9.2, 9.4; 9.6, 9.9, 9.11(d), 80.19, 209.2, 206.226.
  • Exec. Order No. 11988, 42 Fed. Reg. 26,951.
  • PAPPG, at 8, 86, 133, 169.

Headnotes

  • FEMA must review each PA project to ensure that the work complies with applicable federal EHP laws, their implementing regulations, and applicable Executive Orders. It is the Applicant’s responsibility to provide FEMA with enough information to conduct this review.
    • The Applicant did not afford FEMA an opportunity to complete its EHP review or provide documentation demonstrating compliance with EHP requirements.

Conclusion

The Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work and did not provide documentation otherwise demonstrating compliance with EHP requirements and related Executive Orders. Therefore, this appeal is denied.


 

Appeal Letter

SENT VIA EMAIL

Kevin Guthrie                                                                Brittany Juergens

Director                                                                           Account Manager

Florida Division of Emergency Management            Florida Department of Environmental

2555 Shumard Oak Boulevard                                   Protection

Tallahassee, Florida 32399-2100                               3900 Commonwealth Boulevard

                                                                                         Mail Station 75

                                                                                         Tallahassee, Florida 32399-3000

 

Re:  Second Appeal – Florida Department of Environmental Protection, PA ID: 000-U03AE-00 FEMA-4399-DR-FL, Grants Manager Project 133304/Project Worksheet 1897, EHP and Other Compliance 

 

Dear Kevin Guthrie and Brittany Juergens:

 

This is in response to the Florida Division of Emergency Management’s letter dated

May 31, 2024, which transmitted the referenced second appeal on behalf of the Florida Department of Environmental Protection (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of funding in the amount of $882,335.88 for repairs to residences and storage buildings located at the T.H. Stone Memorial St. Joseph Peninsula State Park.

As explained in the enclosed analysis, I have determined the Applicant did not afford FEMA an opportunity to complete its environmental and historical preservation (EHP) review prior to starting work and did not provide documentation otherwise demonstrating compliance with EHP requirements and related Executive Orders. Therefore, this appeal is denied.

This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.

 

                                                                                                   Sincerely,

                                                                                                      /S/

                                                                                                   Robert Pesapane

                                                                                                   Division Director

                                                                                                   Public Assistance Division

Enclosure

cc: Robert D. Samaan

      Regional Administrator

            FEMA Region 4

Appeal Analysis

Background

From October 7 through 19, 2018, Hurricane Michael impacted the state of Florida.[1] The disaster resulted in damage to multiple buildings in the T.H. Stone Memorial St. Joseph Peninsula State Park (Park), operated by the Florida Department of Environmental Protection (Applicant). FEMA created Grants Manager Project 133304 to document the Applicant’s request for $1,061,712.46 to address damage to six buildings in the Park, including the Park Manager Residence, Park Manager Storage, Assistant Park Manager Residence, and Assistant Park Manager Residence Storage buildings. Between June and July 2019, FEMA conducted Site Inspections (SIs) of the six buildings, noting serious damages and replacement needs.[2] Additionally, FEMA’s Environmental and Historic Preservation (EHP) personnel attended the SIs and noted that the Park is in a Special Flood Hazard Area. 

Throughout 2021, FEMA issued Requests for Information (RFIs) to the Applicant to clarify the work completion status, identify specific locations of the work, and support compliance with floodplain management requirements at Title 44 of the Code of Federal Regulations (C.F.R.) Part 9 and Executive Order (EO) 11988, including coordination and approval from the local floodplain administrator. The Applicant responded stating that the Park Manager and Assistant Park Manager Residences have been relocated, and the work already initiated. The Applicant identified the percentage of work completed and the specific locations. The Applicant stated that it consulted with the floodplain administrator but did not provide documentation supporting the consultation. 

On March 29, 2022, FEMA’s EHP personnel completed the Record of Environmental Consideration (REC). The REC asserted that the relocations of the Park Manager and Assistant Park Manager Residences and Storage buildings from Zone AE to Zone VE constitute new constructions in a coastal high hazard area, and do not fall under any exception to the prohibition on new construction because they do not facilitate open space use and are not functionally dependent upon their location in the floodplain. Consequently, the REC found that the repairs for those buildings were non-compliant with EO 11988.[3] 

On May 24, 2022, FEMA issued a Determination Memorandum denying $882,335.88 in funding for the Park Manager and Assistant Park Manager Residences and Storage buildings.[4] FEMA found that the Applicant conducted work prior to FEMA’s required federal EHP review. Additionally, FEMA found that the Park Manager Residence, Park Manager Storage, Assistant Park Manager Residence, and Assistant Park Manager Residence Storage buildings were relocated from Zone AE (high risk) to new locations in Zone VE (coastal high risk) and, accordingly, these projects were not compatible with EO 11988. 

First Appeal

In a letter dated July 22, 2022, the Applicant submitted a first appeal citing to FEMA’s SI findings on where the damaged structures were located (zones AE and VE) and stating that repairs were completed in the same flood zones. Additionally, the Applicant stated that it provided the locations where its buildings would be constructed in its July 21, 2021, RFI response, before construction began, and that it did not receive any additional information from FEMA at that time. The Florida Division of Emergency Management (Recipient) supported the appeal in a September 20, 2022 letter.

The FEMA Region 4 Regional Administrator denied the appeal on January 31, 2024.[5] FEMA found that the Applicant did not provide sufficient documentation to verify EHP compliance regarding the avoidance of potential adverse impacts for actions within a floodplain or coastal high-hazard area. Additionally, FEMA found the Applicant did not provide the local floodplain administrator coordination documentation or justification for relocating the buildings, and thus FEMA was unable to determine if the scope of work complied with all applicable EHP statutes, EOs, and regulations.

Second Appeal

The Applicant submitted a second appeal in a letter dated April 1, 2024, stating that, in its answers to the RFIs, it explained that the reconstruction of the buildings was coordinated with the floodplain administrator, and that it selected where to rebuild based on areas within the Park that had already been impacted. Additionally, the Applicant provided documentation, including documents from the Coastal Construction Control Line Program, which include potential sites and design plans for the buildings. In a letter dated May 31, 2024, the Recipient transmitted the appeal with its support. 

 

Discussion

FEMA may provide Public Assistance (PA) funding for costs to repair, restore, reconstruct, or replace a facility damaged or destroyed by a major disaster.[6] FEMA must review each PA project to ensure that the work complies with applicable federal EHP laws, their implementing regulations, and applicable EOs.[7]If an applicant begins construction work on a project before FEMA is able to conduct its EHP review, the applicant will jeopardize PA funding for the project.[8] It is the applicant’s responsibility to substantiate its claim as eligible.[9]

EO 11988 requires federal agencies to reduce the risk of flood loss, minimize the impact of floods on human safety, health, and welfare, and restore and preserve the natural and beneficial functions of floodplains.[10] FEMA implements and enforces EO 11988 through its regulations at 44 C.F.R. Part 9.[11] These regulations set forth the policy, procedures, and responsibilities to implement and enforce the EO, including the decision-making process, which is referred to as the 8-step process.[12] As part of this process, FEMA must work with the applicant to determine if there are any practicable alternative locations that are outside of the floodplain or in an area of lower risk, if there are alternative actions which serve the same purpose in a different manner, or if no action is the only acceptable alternative.[13] In addition, FEMA’s implementing regulations only allow for new construction or substantial improvement of a structure within a floodplain under limited circumstances.[14] Pursuant to the minimization standards in 44 C.F.R. § 9.11(d), new construction in a floodway or coastal high hazard area is prohibited unless the structure is for a functionally dependent use, or the structure facilitates an open space use.[15] Furthermore, no action may be taken if it is inconsistent with the criteria of the National Flood Insurance Program (NFIP) or any more restrictive Federal, State, or local floodplain management standards.[16] 

Here, the Applicant requested PA funding for the reconstruction of the Park Manager Residence, Park Manager Storage, Assistant Park Manager Residence and Assistant Park Manager Storage buildings in new locations. In its RFI responses, the Applicant provided the locations for the buildings and stated that it already initiated work for the buildings on appeal. FEMA did not have the opportunity to conduct its EHP review prior to the Applicant conducting that work. Therefore, the Applicant prevented FEMA from determining what impact the relocation may have with respect to EHP requirements. Specifically, the Applicant’s initiation of the construction prevented FEMA from considering practicable alternatives that were outside of the floodplain or in an area of lower risk, or alternative actions that could have served the same purpose while avoiding or reducing adverse effects.[17] 

The Applicant also did not demonstrate its relocations complied with FEMA’s minimization standards. In the REC, FEMA documented that the buildings at issue were relocated to a Zone VE floodplain (i.e., a coastal high hazard area) and constituted new constructions that do not facilitate open space use and are not functionally dependent upon their location in the floodplain.[18] On appeal, the Applicant did not dispute these findings or demonstrate that the reconstruction of the buildings for which the Applicant requests funding complies with any of the allowable circumstances for new construction in a floodplain zone. Specifically, the Applicant did not demonstrate that the buildings are functionally dependent or facilitate an open space use. Therefore, the constructions are prohibited under 44 C.F.R. § 9(d)(1).

In addition, 44 C.F.R. Part 9 requires consistency with the NFIP or any more restrictive floodplain management standard. To ensure consistency, FEMA asked the Applicant to demonstrate coordination with and approval from its local floodplain administrator. In its second appeal, the Applicant claims the reconstruction of the new buildings in the new locations was decided in coordination with the floodplain administrator. The Applicant submitted an email it sent to the U.S. Fish and Wildlife Service seeking consultation of the project as well as a letter from the U.S. Army Corps of Engineers authorizing amendments to the plan for the reconstruction of the buildings. However, neither the aforementioned documentation nor any other documentation submitted demonstrates the floodplain administrator’s consultation, approval, or recommendation for the relocation of the buildings on appeal. Therefore, the Applicant has not demonstrated consistency with floodplain management standards.

 

Conclusion

The Applicant did not afford FEMA an opportunity to complete its EHP review prior to starting work and did not provide documentation otherwise demonstrating compliance with EHP requirements and related Executive Orders. Therefore, this appeal is denied.


 

[1] Hurricane Michael resulted in a major disaster for the State of Florida, FEMA-4399-DR-FL, on October 11, 2018. 

[2] See Site Inspection Report (SIR) FEMA-4399-DR-FL, Work Order (WO) #39044, Damage 266964 (July 26, 2019); SIR FEMA-4399-DR-FL, Work Order #39044, Damage 266966 (July 26, 2019).

[3] See Record of Environmental Consideration FEMA-4399-DR-FL, Project Number 133304, at 2, 6

(March 29, 2022). 

[4] FEMA also approved funding, subject to insurance reductions, for work to be conducted on two cabins that are not at issue on appeal. 

[5] The Applicant received the first appeal response by email on February 1, 2024.

[6] Robert T. Stafford Disaster Relief and Emergency Assistance Act § 406, Title 42, United States Code § 5172 (2018); Title 44 of the Code of Federal Regulations (C.F.R.) § 206.226 (2018).

[7] Public Assistance Program and Policy Guide, FP 104-009-2, at 8 (Apr. 1, 2018) [hereinafter PAPPG]. 

[8] Id. at 86.

[9] PAPPG, at 133.

[10] Exec. Order No. 11988, 42 Fed. Reg. 26,951 (May 24, 1977); PAPPG, at 169.

[11] PAPPG, at 169.

[12] 44 C.F.R. § 9.6; PAPPG, at 169.

[13] See 44 C.F.R. §§ 9.6 (discussing practicable alternatives in steps 3 and 6 of the 8-step process), 9.9(b).

[14] 44 C.F.R. § 9.11(d)(1).

[15] Id. ‘Functionally dependent’ use means a use which cannot perform its intended purpose unless it is located in close proximity to water. 44 C.F.R. § 9.4. Part 9 does not define “open space use” but in other Parts of 44 C.F.R., open space allowable uses generally include outdoor recreational use and do not generally include “walled buildings.” See, e.g., 44 C.F.R. §§ 80.19, 209.2. 

[16] 44 C.F.R. § 9.11(d)(6).

[17] FEMA is required to analyze practicable alternatives prior to taking any action. See 44 C.F.R. § 9.2(a); Exec. Order No. 11988 § 2(a)(1)-(2). In its request for information response, the Applicant recognized that it had two other alternate locations for the construction of the buildings on appeal but selected the one in Zone VE because it already had an environmental impact review and was approved by the Coastal Construction Control Line program.

[18] Zone AE is inherently lower risk than Zone VE due to the presence of high velocity wave action in the VE zone.

Last updated