When should the SF-425 Federal Financial Report be provided to FEMA?
SF-425, Federal Financial Report to FEMA on a quarterly basis throughout the grant awards period of performance, including any partial quarters in which the period of performance is open. States/territories must submit the report even if no grant award activity occurs during a given quarter.
The following reporting periods and due dates apply for the SF-425 Federal Financial Report:
Reporting Period | Report Due Date |
---|---|
October 1 – December 31 | January 30 |
January 1 – March 31 | April 30 |
April 1 – June 30 | July 30 |
July 1 – September 30 | October 30 |