Scope of Work
Appeal Brief
Disaster | 1984-DR-SD |
Applicant | City of Pierre |
Appeal Type | Second |
PA ID# | 065-49600-00 |
PW ID# | 2432 |
Date Signed | 2015-05-27T00:00:00 |
Conclusion: The damage to the Applicant’s three sewer lines and a manhole was caused by the disaster and the work performed by the Applicant’s contractor under the original contract and a subsequent change order was necessary to accomplish the needed repairs. The Applicant’s procurement of the original contract appropriately utilized small purchase procedures, as the total cost of the contract was less than $150,000. The Applicant’s use of noncompetitive procedures to award a sole-source change order to address additional damage discovered during the repair work was appropriate, as it was infeasible to have conducted a competitive procurement and the public emergency would not permit delay resulting from competitive solicitation. The Applicant did not, however, perform an appropriate cost analysis of the change order, which is a violation of the procurement standards.
Summary Paragraph
In 2011, significant flooding caused erosion and degradation of the sanitary sewer system operated by the City of Pierre (Applicant), resulting in a sinkhole stretching along a sewer line from a manhole. The Applicant received two bids from contractors to perform permanent repairs to the sinkhole and remove and replace the sewer line. The city awarded the contract to the lower bidder. During excavation and repair, additional damage was discovered on two additional sewer lines and the manhole. On November 29, 2011, a change order was issued for the additional repair work, totaling $237,244.86. FEMA approved Project Worksheet (PW) 2432 for $90,775.33, covering the costs of temporary repair work, direct administrative costs, the initial contract for the permanent repair of the sewer line (which was $86,000.00), and a contract estimate for curb and gutter work. PW 2432 did not include the costs of work performed under the $237,244.86 change order to the contract because, FEMA determined, there was a “lack of specific documentation regarding costs and quantities” and “proof that the damages were flood-related.” The Applicant appealed this decision, and the Acting Regional Administrator approved the appeal in part determining that neither the initial contract procurement nor the change order comported with applicable procurement regulations. On second appeal, the Applicant argues that its actions were justified under applicable procurement laws, and that the entire scope of work is eligible for PA funding.
Authorities
- 44 C.F.R. § 206.223(a)
- 44 C.F.R. §§ 13.36 and 13.43
- 44 C.F.R. §207.6
Headnotes
- Under 44 C.F.R. § 206.223(a), for any item of work to be eligible for financial assistance, it must, among other things, be required as a result of the emergency or major disaster event.
- Under 44 C.F.R. Part 13, local government subgrantees must follow procurement procedures that reflect applicable state and local laws, provided that they also conform to applicable federal law and the standards set forth in 44 C.F.R. § 13.36. Generally, procurements must be undertaken in a way that provides for full and open competition. Federal regulations provide for four types of procurement methods: by small purchase procedures, by sealed bids, by competitive proposals, and by noncompetitive proposals (when warranted).
- Small purchase procedures was an appropriate method of procurement for the original procurement. The contract was awarded for less than the simplified acquisition threshold of $150,000, and the Applicant solicited bids from an adequate number of sources, ultimately awarding the contract to the lower of the two bids received. The change to the scope of work increasing the cost of the contract above the simplified acquisition threshold was not foreseeable at the time of award.
- Procurement by noncompetitive proposals was an appropriate method of procurement for the change order. Repairing the sewer lines without undue further delay was critical, given impending winter temperatures and continuing sewer backups in the surrounding downtown district. It was, therefore, infeasible to have conducted a competitive procurement and the public emergency would not permit delay resulting from competitive solicitation.
- The Applicant did not, however, complete a cost analysis as required under a noncompetitive procurement.
- Disaster Assistance Policy (DAP) 9525.9, Section 324 Management Costs and Direct Administrative Costs, Section VII(D)(1).
Direct Administrative Costs include costs that can be tracked, charged and accounted for directly to a specific project, such as staff time to complete field inspection and preparation of a PW. Direct costs are limited to actual reasonable costs incurred for a specific project. The Applicant provided a list of six staff members it asserts engaged in administrative activities pertaining to PW 2432, but failed to include supporting documentation, such as timesheets, establishing that the work was actually performed.
Appeal Letter
May 27, 2015
Kristi Turman
Director
South Dakota Office of Emergency Management
118 West Capitol Avenue
Pierre, South Dakota 57501
Re: Second Appeal—City of Pierre, Sanitary Sewer Line Repair, FEMA-1984-DR-SD, Project Worksheet 2432
Dear Ms. Turman:
This is in response to a letter from your office dated October 25, 2013, which transmitted the referenced second appeal on behalf of the City of Pierre (Applicant). The Applicant is appealing the Department of Homeland Security’s Federal Emergency Management Agency (FEMA) denial of its request for certain costs associated with sewer line repairs caused by heavy flooding.
As explained in the enclosed analysis, FEMA is partially approving the Applicant’s second appeal. The damage to the sewer lines and manhole was caused by the disaster event, and the work as described in the change order was necessary to accomplish the needed repairs. The Applicant complied with the method of procurement requirements under 44 C.F.R. § 13.36(d) for both the original procurement and the change order, but failed to comply with the cost analysis requirement for the change order required by 44 C.F.R. § 13.36(f). Notwithstanding this noncompliance, FEMA will not take enforcement action by reducing the otherwise eligible costs incurred by the Applicant for eligible work. FEMA will, therefore, increase the amount awarded under PW 2432 by an additional $213,570.86 for costs incurred under the change order, $3,397.10 for the manhole, $2,359.85 for curb and gutter repair and replacement, and $5,666.05 for direct administrative costs related to this project.
Please inform the Applicant of my decision. This determination constitutes the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.
Sincerely,
/s/
William W. Roche
Director
Public Assistance Division
Enclosure
cc: Sharon Loper
Acting Regional Administrator
FEMA Region VIII
Appeal Analysis
Background
In the spring and summer of 2011, warm temperatures caused significant runoff and flooding in the state of South Dakota following a winter with above-normal snowfall. On May 13, 2011, the President declared a major disaster for the state (FEMA-1984-DR-SD), with an incident period of March 11 to July 22, 2011.
The flooding caused erosion and degradation of the sanitary sewer system operated by the City of Pierre (Applicant). The sewer system delivers sewage to the Applicant’s wastewater treatment plant. A 72-foot long section of a 10-inch diameter clay sanitary sewer pipe on Missouri Avenue failed, creating a sinkhole that began developing during the disaster incident period. The sinkhole stretched due east along the sewer line (the “East Line” to Pierre Street) from a manhole that serves as a connection point between additional sewer lines and a lift station. The Applicant used contract services, force account labor, and force account equipment to address resulting sewer backups, bypass pumping, and perform temporary repairs to the sinkhole.
The Applicant received two bids from contractors to perform permanent repairs to the sinkhole and remove and replace the sewer line, one bid for $86,000.00 and another for $160,400.00. On October 25, 2011, the Applicant awarded a contract to the lower bidder, Morris, Inc. (the “Contractor”). The contract included work immediately adjacent to the manhole and included removal of a minimum of the top half of the impacted manhole. Under the contract, the Contractor was responsible for providing all materials, except for surface gravel, and the Applicant was responsible for replacing asphalt surface material, closing the water line valve, and bypass pumping.
On October 26, 2011, the Applicant issued a notice to proceed to the Contractor. During excavation and repair and after the pipe was exposed, additional damage was discovered on two additional sewer lines and the manhole. On November 29, 2011, a change order was issued for work to include: (1) removal of the manhole and placement of a concrete base under the replacement manhole, (2) excavation and removal of a damaged 12-inch line to the lift station to the north (the “North Line” to lift station), (3) excavation and removal of a damaged 10-inch line flowing into the manhole from the west and installation of a new line (the “West Line” to Fort Street), and (4) installation of sheet piling to protect structures and laborers. The change order amounted to $237,244.86.
On April 13, 2012, FEMA obligated $90,775.33 in Project Worksheet (PW) 2432, covering the contract and force account work and materials associated with the temporary repair of the sinkhole ($3,484.60), direct administrative costs (DAC) ($94.73), and the initial contract for the permanent repair of the sewer line ($86,000.00), plus a contract estimate for curb and gutter work ($1,196.00).[1] PW 2432 did not include the costs of work performed under the $237,244.86 change order to the contract because, FEMA determined, there was a “lack of specific documentation regarding costs and quantities” and “proof that the damages were flood-related.” According to FEMA, without documentation supporting the $237,244.86 lump-sum change order, it was not possible to determine the reasonableness of those costs. FEMA’s PW notation also stated that the additional damage was discovered after the initial site inspection and had not been inspected by FEMA.
First Appeal
The Applicant submitted a first appeal to the South Dakota Department of Public Safety (Grantee) in a letter dated May 18, 2012, seeking reimbursement of the $237,244.86 change order amount. The Grantee forwarded the letter to FEMA Region VIII in a letter dated July 3, 2012, after requesting and obtaining additional information from the Applicant. The Applicant asserted that the Missouri Avenue manhole displayed obvious displacement following the disaster, with the displacement resulting in the shearing of the three sewer lines entering the manhole. Displaced manholes and sinkholes arose throughout the city, the Applicant explained, with other PWs written to document the costs of their repair. The Applicant stated that the failure became visible around the manhole before excavation began but that the specific lines affected by the manhole’s displacement were not known until a visual inspection after excavation. The damage to the additional lines and manhole became apparent only after the Contractor exposed the structure, the Applicant asserted. Thus, rather than being a “singular repair,” the applicant explained, the repair “became a three[-]phase project involving three excavations and repairs.” According to the Applicant, the Contractor justified the increased costs of $237,244.86, and the Applicant approved the change order in that amount in accordance with applicable procurement procedures. The Applicant noted that the deep repair, water and materials infiltration, nearby utilities, need for sheet piling, and other factors made the project complex and costly.
On July 3, 2013, after issuing multiple requests for information and receiving the requested information from the Applicant, the Acting Regional Administrator (RA) issued a decision partially granting the appeal. Regarding whether the damage to the system was caused by the disaster, the Acting RA stated that, without knowing the condition of the manhole immediately prior to the appearance of the sinkhole, it was not possible to determine how the damage to the system occurred. However, the Acting RA accepted the Applicant’s assertions that the system was intact prior to the disaster event and that the damage to the sewer lines was caused by the disaster but rejected the notion that the manhole itself was damaged, stating that the Applicant merely asserted that a new manhole was placed to “ensure a proper seal.” Regarding eligible work, the Acting RA concluded that the scope of work under both the original contract and the change order included increased and duplicative work and that eligible work included (1) excavation and replacement of 51.9 feet of 10-inch East Line lateral from the manhole toward Pierre Street, along with pea gravel bedding; (2) excavation and replacement of 12 feet of 10-inch West Line lateral from the manhole toward Fort Street, along with pea gravel bedding; (3) excavation and replacement of 20 feet of 12-inch North Line lateral from the manhole toward the lift station, along with pea gravel bedding; and (4) stabilization of the manhole location with gravel and placement of a new concrete base.
The Acting RA also found that the Applicant improperly procured both the original contract and the change order. As to the original contract, the Acting RA stated that the Applicant failed to publicly advertise its solicitation for bids and, instead, merely solicited invitations to bid from local, capable contractors. The Acting RA also stated that the need for additional work was not discovered until after the contract completion date of November 21, 2011. As to the change order, the Acting RA stated that the Applicant failed to perform a necessary cost analysis and approved the change on a lump-sum basis, a change that increased the contract price by 276 percent. The Acting RA concluded that this increase could not be considered reasonable.
The Acting RA sought to establish reasonable costs based on FEMA’s Cost Estimating Format (CEF). Applying the CEF the Acting RA, estimated total eligible costs for the work completed amounted to $114,449.33--$23,674.00 above the obligated amount.
Finally, the Acting RA concluded that no documentation was provided supporting $1,241.00 in claimed Direct Administrative Costs, $2,096.85 in force account labor costs, and $897.00 in force account equipment costs.
The Acting RA obligated an additional $23,674.00, representing additional reasonable costs arrived at using the CEF and based on what he determined to be eligible work.
Second Appeal
The Applicant submitted a second appeal in a letter dated August 28, 2013. The Applicant argues that, given the circumstances it faced, its procurement of both the original contract and the change order complied with applicable procurement laws and procedures. As to the original contract, the Applicant noted that, at the time of the repair, the Missouri River flooding resulted in significantly elevated underground water levels, leaving its sanitary sewer line near the river under 20 feet of water, negatively affecting manholes and the lift station. According to the Applicant, federal and state procurement laws allow for emergency procurement when a threat exists to public health, welfare, or safety, or when a public emergency requires it. The Applicant asserts that sewer line breaks and resulting sewage backup and bypass procedures constituted such a threat and emergency. Moreover, the Applicant states, under federal procurement regulations, small purchases may be accomplished by obtaining several price quotes from different sources; three contractors attended the bid opening and reviewed the original contract scope of work, the Applicant explained, and two submitted bids. The Applicant noted that it accepted the lower bid of $86,000.00, under the small purchase threshold.
Regarding the change order procurement, the Applicant cites a variety of factors it asserts justified its decision under state law, federal law, and FEMA policy to proceed with additional repairs to the newly discovered damage without competing the work. The Applicant points out that the breaks in the three lines affected the main sewer line, which serves more than half of the city’s population. The Applicant notes that above-normal precipitation continued during the repairs and that, given the extended length of the project, repair work—which involved exposed utilities and structures—would take place during below-freezing temperatures as winter set in. The freezing temperatures would affect not only the repairs but also bypass operations, the Applicant argues. In addition, the Applicant notes, the Contractor had already installed sheetpiling, which was actively protecting the site, and was the sole source of sheetpiling in the area. The Applicant also notes the numerous other sewer repairs were required following the disaster event and asserts that utility repairs and levee removals in progress in dozens of counties across South Dakota and in the surrounding state affected contractor availability. Thus, the Applicant argues, the Contractor, already in place, was the only practicable source to continue the repair work.
The Applicant also argues that the costs of the project, including the additional repairs under the change order (totaling $323,244.86), were reasonable and in line with other sewer repair work at the time. The Applicant states that the project’s total cost per day, $10,774.83, was approximately $2,500.00 per day less than the per-day average sewer repair bid that the Applicant reviewed in 2011 following the disaster.
The Applicant asserts that total project costs (including costs captured on PW 2425) amount to $370,612.96. After taking into account funding provided thus far—the original $90,775.33 obligated in PW 2432; the $23,674.00 in additional costs awarded by the RA; and $7,095.00 for asphalt repairs associated with the site captured in PW 2425—the Applicant requests an additional $249,163.36 for the repairs.[2] The Applicant also seeks an additional $5,666.05 in DAC:
| Total Project Cost (Requested by Applicant) | FEMA Eligible after 1st Appeal | Difference |
PW 2432 |
|
|
|
Work Completed | 3,484.60 | 3,484.60 | 0.00 |
Contract Work | 86,000.00 | 86,000.00 | 0.00 |
Curb and Gutter | 3,555.85 | 1,196.00 | 2,359.85 |
Additional Costs: |
|
|
|
Contract (first appeal) | 237,244.86 | 23,674.00 | 213,570.86 |
Manhole | 3,397.10 |
| 3,397.10 |
DAC |
| 94.73 |
|
Sub-total PW 2432 | 333,682.41 | 114,449.33 | 219,233.08 |
|
|
|
|
Lift station (other PW) | 8,697.64 |
| 8,697.64 |
Asphalt repair (other PW) | 28,232.91 | 7,095.81 | 21,137.10 |
Sub-total (includes other PW) | 370,612.96 | 121,545.14 | 249,067.822 |
|
|
|
|
DAC (only PW 2432) | 5,666.05 |
| 5,666.05 |
|
|
|
|
Total (PW 2432) | 339,348.46 | 114,449.33 | 224,899.13 |
Total (includes other PWs) | 376,279.01 | 121,545.14 | 254,733.87 |
The Grantee transmitted the second appeal to the FEMA Region VIII Acting RA in a letter dated October 25, 2013. Applicant representatives provided a presentation to FEMA reiterating and supplementing points raised on second appeal on January 27, 2014.
Discussion
Damage and Scope of Work
Section 406 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act (“Stafford Act”) authorizes FEMA to provide grant assistance to states, local governments, and certain non-profit organizations for the repair and replacement of facilities damaged or destroyed by a major disaster.[3] FEMA administratively categorizes this work as “permanent work,” Public Assistance Categories C through G. To be eligible for Public Assistance, an item of work must be required as a direct result of the designated event under a major disaster declaration.[4] Work to repair damage that results from a cause other than the designated event outside the incident period (such as a pre- or post-disaster rain, wind, flooding, storms, or normal weather conditions) is not eligible, and it is an applicant’s responsibility to show that the damage is disaster-related.
On first appeal the RA concluded that eligible work included (1) excavation and replacement of 51.9 feet of 10-inch East Line lateral from the manhole toward Pierre Street, along with pea gravel bedding; (2) excavation and replacement of 12 feet of 10-inch West Line lateral from the manhole toward Fort Street, along with pea gravel bedding; (3) excavation and replacement of 20 feet of 12-inch North Line lateral from the manhole toward the lift station, along with pea gravel bedding; and (4) stabilization of the manhole location with gravel and placement of a new concrete base. The RA rejected the Applicant’s assertions that the manhole was damaged by the disaster because the Applicant did not provide supporting document. After a review of the Applicant’s appeal submissions, FEMA concludes that the Applicant has provided documentation—in the form of maps, photographs, reports, charts, e-mail communications, and other materials—sufficiently demonstrating that the damage to the three sewer lines and manhole was caused by the disaster event and that all of the repair work as described in the change order was necessary.
Procurement
There are three procurement-related issues presented under the second appeal: (1) whether the method of procurement used by the applicant for the original procurement complied with 44 C.F.R. § 13.36(d); (2) whether the procurement method followed by the applicant for the change order complied with 44 C.F.R. § 13.36(d); and (3) whether the applicant conducted the proper cost or price analysis for the change order. An overview of procurement standards applicable to the issues presented is provided below, followed by an analysis of each issue.
Overview of the Applicable Procurement Standards at 44 C.F.R. § 13.36
Financial assistance provided under the Public Assistance Grant Program can be used for the cost of eligible work completed through contracts procured by a local government applicant.[5] As a condition of receiving financial assistance for these contract costs, a local government’s procurement and resulting contract must comply with the standards set forth at 44 C.F.R. § 13.36. This regulation requires a local government to use its own procurement procedures which reflect applicable state and local laws and regulations, provided that the procurements conform to applicable federal law and the federal procurement standards set forth at 44 C.F.R. § 13.36(b)-(i). It is important to recognize that a procurement may, in some circumstances, comply with state and local law and regulations, but not meet the minimum federal procurement standards—such a procurement would be noncompliant with 44 C.F.R. § 13.36.
These federal procurement standards require local government subgrantees to, among other things, conduct all procurement transactions in a manner providing full and open competition consistent with the standards at 44 C.F.R. § 13.36.[6] Full and open competition, although not defined by the regulation, generally means that a complete requirement is publicly solicited and all responsible sources are permitted to compete.[7]
The regulation also sets forth the three competitive methods of procurement to be followed by a local government, which include procurement by small purchase procedures, sealed bidding, and competitive proposals.[8] First, small purchase procedures are those relatively simple and informal procurement methods for securing services, supplies, or other property that do not cost more than the simplified acquisition threshold, which was $150,000 at the time of major disaster FEMA-1984-DR.[9] If small purchase procedures are used, a local government must obtain price or rate quotations from an adequate number of qualified sources.[10] Second, under sealed bidding, a local government publicly solicits bids and a firm-fixed price contract is awarded to the responsible bidder whose bid, conforming with all the material terms and conditions of the invitation for bids, is the lowest in price.[11] The sealed bid method is the preferred method for procuring construction if certain conditions apply.[12] Third, the technique of competitive proposals is normally conducted with more than one source submitting an offer, and either a fixed-price or cost-reimbursement contract is awarded.[13] This method is generally used when conditions are not appropriate for the use of sealed bids.[14]
In addition to the three competitive methods, the regulation does permit a local government to utilize the procurement through noncompetitive proposal method. A local government can only use this method, however, in cases where the award of a contract is infeasible under small purchase procedures, sealed bidding, or competitive proposals and where one of following four alternative conditions applies: (1) the item is available only from a single source; (2) public exigency or emergency for the requirement will not permit delay resulting from competitive solicitation; (3) the awarding agency authorizes noncompetitive proposals; or (4) after solicitation of a number of sources, competition is determined inadequate.[15]
The regulation at 44 C.F.R. § 13.36(f) requires a local government to perform a price or cost analysis in connection with every procurement action, including contract modifications. A cost analysis involves the verification of proposed cost data, projections of that data, and evaluation of the specific elements of costs and profits.[16] A cost analysis is required for sole source procurements, including contract modifications or change orders, unless price reasonableness can be established on the basis of a catalog or market price of a commercial product sold in substantial quantities to general public or based on prices set by law or regulation.[17] A price analysis will be used in all other instances to determine the reasonableness of the proposed contract price.[18]
Once a contract is awarded, a local government may need to make changes to that contract to react to newly encountered circumstances, fix inaccurate or defective specifications, or modify the work to ensure the contract meets the local government’s requirements. A contract “change” is any addition, subtraction, or modification of work under a contract during contract performance.[19] Notwithstanding the need to make appropriate contract changes, a local government may not make a “cardinal change” to a contract so as to circumvent the requirements of 44 C.F.R. § 13.36 for full and open competition. A cardinal change is a significant change in contract work (property or services) that causes a major deviation from the original purpose of the work or the intended method of achievement, or causes a revision of contract work so extensive, significant, or cumulative that, in effect, the contractor is required to perform very different work from that described in the original contract.[20] A modification that comprises a cardinal change constitutes a sole source award, and FEMA evaluates such a modification to determine if the conditions precedent for a noncompetitive procurement at 44 C.F.R. § 13.36(d)(4) have been met.
Procurement of the Original Contract
The Acting Regional Administrator determined in the first appeal that the Applicant failed to adhere to the procedural requirements of sealed bidding at 44 C.F.R. § 13.36(d)(2) when procuring the original contract for $86,000. Specifically, the Applicant failed to publicly advertise its invitation for bids and, instead, only solicited invitations to bid from local, capable contractors.[21] In the second appeal, the Applicant has asserted, among other things, that the contract was for less than the simplified acquisition threshold, such that it could avail itself of the procurement by small purchase procedures method of procurement under 44 C.F.R. § 13.36(d)(2).[22]
The regulation at 44 C.F.R. § 13.36(d)(1) provides that small purchase procedures are those relatively simple and informal procurement methods for securing services, supplies, or other property that do not cost more than the simplified acquisition threshold, which was $150,000 at the time of major disaster FEMA-1984-DR.[23] A local government may not break out a larger procurement merely to gain advantage of small purchase procedures. Similarly, a local government may not limit the size of a procurement to only a portion of a known requirement in order to gain advantage of small purchase procedures and then, to fulfill the entire requirement, later issue follow-on change orders that bring the procurement above the simplified acquisition threshold.
FEMA has determined that the Applicant was not required to use sealed bidding for the original procurement and that it was appropriate for the Applicant to have utilized the small purchase procedure method of procurement. When evaluating whether it was appropriate for a local government to have used small purchase procedures, FEMA will review whether the supplies or services to be acquired were initially estimated to not exceed the simplified acquisition threshold or whether the acquisition did, in fact, exceed the threshold. In this case, the Applicant acquired services to repair the single sewer line and sinkhole on Missouri Avenue that cost $86,000, which falls below the simplified acquisition threshold. The documentation provided by the Applicant also indicates that the additional damage discovered after work began on this contract was unknown at the time of the original procurement, and that the Applicant developed the scope for the original procurement based on its inspection of the site and judgment as to the work necessary to repair disaster damage. There is no indication that the Applicant improperly limited a known, larger requirement so as to avail itself of small purchase procedures.
In addition to demonstrating that the acquisition falls below the simplified acquisition threshold, when small purchase procedures are used, a local government must obtain price or rate quotations from an adequate number of qualified sources.[24] FEMA has generally interpreted an “adequate number” of sources under 44 C.F.R. § 13.36(d)(1) to be at least three, although what is adequate will depend upon the facts and circumstances surrounding a particular procurement. [25] The Applicant asserted that it solicited numerous local contractors to submit quotes for the project, with two contractors responding and submitting bids. Although only receiving two bids, the facts and circumstances indicate that it was a reasonable decision not to delay on moving forward with the procurement by going back out and seeking one additional bid from those contractors already solicited or from additional contractors not previously solicited. The Applicant asserted that the water elevation line was above the sewer line at the time the original contract was written. The water, which had a significant and negative effect on the sanitary sewers, manholes, and lift station, made time of the essence to effectuate the repairs and address threats to public health caused by the existing sewer leekage and potential future leekage.[26] FEMA has, under these specific facts and circumstances, determined that the Applicant obtained price or rate quotations from an adequate number of qualified sources for the original procurement.
Procurement Method Used for the Change Order
The Acting Regional Administrator determined in the first appeal that the Applicant failed to adhere to the requirements of 44 C.F.R. § 13.36 when it procured the change order to the original contract, making specific reference to the failure of the Applicant to perform a cost analysis pursuant to 44 C.F.R. § 13.36(f). The first appeal response and analysis, however, did not specifically analyze the method of procurement used to obtain the change order. Notwithstanding, it is implied from the first appeal decision that the Acting Regional Administrator found issue with the Applicant’s noncompetitive method of procuring the change order (as is evidenced by the Applicant and Grantee specifically addressing this issue on second appeal), and FEMA will address this issue as part of the second appeal. The issue of a cost analysis is addressed in the following subsection.
A contract “change” is any addition, subtraction, or modification of work under a contract during contract performance.[27] The first step in analyzing a contract change is to determine whether the change is within the scope of the original procurement. If it is, then the change order is simply part of the original procurement, which means that such a change would be permissible if the Applicant had complied with all relevant procurement standards during the original procurement. FEMA treats a cardinal change, on the other hand, quite differently. A cardinal change is a significant change in contract work (property or services) that causes a major deviation from the original purpose of the work or the intended method of achievement, or causes a revision of contract work so extensive, significant, or cumulative that, in effect, the contractor is required to perform very different work from that described in the original contract.[28] In effect a cardinal change creates a new procurement action that must meet all relevant procurement standards. Cardinal changes cannot be identified by assigning a specific percentage, dollar value, number of changes, or other objective measure that would apply in all cases.
FEMA has determined that the change order at issue comprised a cardinal change to the original contract based on the significant increase to the amount and type of repair work and total cost. The scope of work under the original contract included excavation and repair of the 10-inch line to the east of the manhole and removal and reset of a minimum of the top half of the manhole. The Applicant explained that the depth of the repair work was significantly increased from 16 to 20 feet in the change order and prompted a great deal of additional work, including the excavation and replacement of 12 feet of line west of the manhole, excavation and replacement of 16 feet of line to the north, and placement of a concrete pad beneath the new manhole. The cost of this work increased the costs of the contract by $237,244.86, which is an almost 300% increase to the original fixed-price contract for $86,000.
A contract change that comprises a cardinal change constitutes a sole source award, and FEMA evaluates such a modification to determine if the conditions precedent for a noncompetitive procurement at 44 C.F.R. § 13.36(d)(4) have been met. This regulation does permit a local government to utilize the procurement through noncompetitive proposal method, but only when two conditions precedent are met. The first condition is that the award of contract is infeasible under small purchase procedures, sealed bidding, or competitive proposals, and the second condition precedent is that one of following four alternative conditions apply: (1) the item is available only from a single source; (2) the public exigency or emergency for the requirement will not permit delay resulting from competitive solicitation; (3) the awarding agency authorizes noncompetitive proposals; or (4) after solicitation of a number of sources, competition is determined inadequate. A Public Assistance applicant’s failure to plan does not provide sufficient justification for procurement by noncompetitive proposals or otherwise conducting a procurement through less than full and open competition.
The regulation does not define the term “infeasible,” but FEMA generally defines the term as not feasible, not practicable, or not capable of being done, effected, or accomplished.[29] Whether or not a form of competitive procurement is feasible includes an analysis of the facts and circumstances of a particular procurement and is often intertwined with the analysis of the second condition precedent. The Applicant did not provide any information indicating how long it would have taken to have performed a competitive procurement as part of its first or second appeal. Although no such information was submitted, we understand that the amount of the procurement at issue would have necessitated the Applicant to follow formal advertisement procedures under state law, which requires publication of the advertisement at least ten days before the opening of bids or proposals.[30] FEMA estimates, in the best case, it would also have taken at least 2 weeks to prepare the solicitation, evaluate the bids or proposals upon receipt, resolve any potential protests, prepare a contract, and submit the contract for approval to the cognizant city official(s). FEMA has concluded that it was not feasible to complete the procurement—at the very least—for 3 ½ weeks from the time the Applicant defined the scope of the additional damages on or about November 14, which would be December 8.
In addition to the period of infeasibility, the Applicant must also demonstrate that the second condition precedent for using noncompetitive proposals has been met. The applicable circumstance for discussion in this case is that “the public exigency or emergency for the requirement will not permit delay resulting from competitive solicitation.” This second condition precedent is crucial for demonstrating that the Applicant had to move forward with procuring the services and could not wait for the competitive process to be completed.
The term “exigency” is not necessarily the same as the term “emergency,” although the terms are often used interchangeably. An “exigency” is generally defined as something that is necessary in a particular situation that requires or demands immediate aid or action.[31] By comparison, the term “emergency” means an unexpected and usually dangerous situation that calls for immediate action.[32] One of the key distinctions between the terms, accordingly, is that an emergency will typically involve a threat to the public or private property or some other form of dangerous situation, whereas an exigency is not necessarily so limited.[33]
FEMA has determined that the Applicant has demonstrated that the public emergency would not permit delay resulting from competitive solicitation. Upon defining the additional damage on or about November 14, repairing the sewer lines without delay was critical, given that the Applicant needed to work immediately to address the existing and potential additional sewage leakage resulting from the damage to the sewer lines and manhole that presented the threat of bacteria and viruses escaping to surrounding areas. The Applicant pointed out that sewer backups continued in the surrounding downtown district and water lines, and that winter temperatures would soon threaten sewage bypass and dewatering operations which would result in the backup of the trunkline, which would have affected homes and businesses. The forthcoming winter temperature would also preclude the ability to actually effectuate the repairs due to freezing of the ground in which the work took place.
FEMA has also determined that the Applicant did not create or otherwise contribute to the public emergency because of the Applicant’s failure to plan. The sinkhole first appeared in June 2011 and the Applicant did not move forward with procuring the original contract to effectuate the permanent repairs until October 2011. It was during the course of these repairs that the Applicant discovered the additional damage and need for significant, additional work, and it was the impending winter temperatures upon which the Applicant has, in part, relied upon in demonstrating the public emergency that precluded delay from a competitive solicitation. As such, if there were no adequate justification for the four-month delay in originally procuring the needed services, then the Applicant could not justify a noncompetitive procurement through its failure to make a timely procurement.
But the Applicant, in this case, has provided adequate justification for the four-month delay. Specifically, the U.S. Army Corps of Engineers (USACE) was making various discharges from (the Oahe Dam) that impacted the water levels at the area of the damage, and the Applicant waited until the declared end of the event by the USACE before developing the scope of work to make the repairs and moving forward with the procurement. The declared end of the USACE event occurred on October 17, 2011, and the Applicant then developed a scope of work and completed small purchase procedures by October 25, 2011.
It is important to recognize that the duration of “infeasibility” is not necessarily the same as the period of emergency. As stated above, in order to use the procurement through noncompetitive proposals, the award of the contract must be “infeasible” under small purchase procedures, sealed bids, or competitive proposals. And it may be the case that—while it may be infeasible in the short-term to pursue a competitive procurement process in light of an emergency that does not permit delay—it may be possible and practicable for the local government to proceed with a competitive procurement to transition the work into a contract that meets the full and open competition requirements of 44 C.F.R. § 13.36. Such a situation, however, is not present under the facts presented.
First, assuming a period of infeasibility that extended 3 weeks from November 14, a contractor would not have begun work until on or about December 8. The contractor at issue here completed the original repairs on November 16, 2011, and began work on the change order on November 29, 2011, finishing all work by December 23, 2011. This means that the contractor would have completed a substantial portion of the work under the change order by the time a new contractor would have been able to take over that work. Second, in light of the fact that the Applicant needed the first contractor to begin work quickly, it would have been impractical for the Applicant to try and develop a precise scope of work for a follow-on contract. The work at issue, in other words, was not divisible in such a way so as to enable any level or precision in determining what work would be remaining to be done at the time the follow-on contract was awarded. Third, transition from the initial to the second contractor would have delayed the project even further, as the initial contractor would have had to remove the sheet piling driven into the ground to isolate and protect the area of work before the new contractor would begin work (which would involve putting new sheet piling in). The removal of the sheet piling may also have caused additional destabilization and damage to the area.
Cost Analysis for the Change Order
The Acting Regional Administrator determined in the first appeal that the Applicant failed to perform a cost analysis pursuant to 44 C.F.R. § 13.36(f) for the change order. The regulation at 44 C.F.R. § 13.36(f) requires a local government to perform cost analysis for sole source procurements, including contract modifications or change orders, unless price reasonableness can be established on the basis of a catalog or market price of a commercial product sold in substantial quantities to the general public or based on prices set by law or regulation.[34] As pointed out in the previous subsection, the Applicant conducted a sole source procurement when it awarded the change order to its existing contractor, meaning that it needed to perform a cost analysis. This is also not a situation falling under the exception from performing a cost analysis under 44 C.F.R. § 13.36(f), as (1) the repair of a sewer system is not a commercial product sold in substantial quantities to the general public and (2) the Applicant provided no information establishing that the cost to make the repairs was based on law or regulation. Therefore, the Applicant was required to conduct a cost analysis.
A cost analysis involves the verification of proposed cost data, projections of that data, and evaluation of the specific elements of costs and profits.[35] The Applicant did not provide any documentation that it conducted such an analysis at the time of the change order, meaning that the Applicant failed to meet the requirements of the 44 C.F.R. § 13.36(f)(1). Notwithstanding this noncompliance, FEMA has determined it will exercise its discretion to not take enforcement action under 44 C.F.R. § 13.43.
Eligible Costs
FEMA has concluded that all work performed under the change order (including replacement of the manhole) is eligible as permanent work under the Public Assistance Program and, in light of this conclusion, must evaluate the costs for eligibility. This includes (1) evaluating the costs for that work the Acting Regional Administrator determined was eligible in the first appeal, but for which he only provided a portion of the requested costs; and (2) evaluating the costs of the additional work that FEMA has determined eligible under this second appeal related to the manhole; and (3) other costs. The Applicant seeks total, additional costs of $249,163.36 under this second appeal as detailed below:
- An additional $213,570.86 for the change order portion of the work (the difference between the $237,244.86 change order amount and the $23,674.00 awarded in the first appeal decision).
- An additional $3,397.10 for the manhole.
- An additional $2,359.85 for curb and gutter work ($3,555.85 that the applicant asserts represents actual costs, less the $1,196.00 awarded in PW 2432).
- An additional $8,697.64 for repair work related to the lift station.
- An additional $21,137.10 for asphalt repair work.
As it relates to work under the change order, the Public Assistance Guide describes the following ways reasonable costs may be established: historic documentation for similar work, average costs for similar work in the area, published unit costs from national cost estimating databases, FEMA cost codes, and equipment rates.[36] The Applicant has provided bid and award amounts and project duration for twelve other disaster-related sewer repair projects captured in other PWs. The average per-day contract award amount was $13,278.57, according to the Applicant’s analysis. In comparison, the initial contract procurement of $86,000.00, with an anticipated project length of seven days, amounted to $12,285.71 per day. The $237,244.86 change order, for work over 25 days, amounted to $9,489.79 per day. The entire $323,244.86 project, which took place over 30 days, averaged $10,744.83 per day, more than $2,500.00 less than the overall per-day average for the Applicant’s sewer repair projects.
FEMA has also independently evaluated the costs for the work performed under the change order.[37] FEMA’s approach of comparing similar work performed in the same city, around the same time frame for damages caused by the same event to determine reasonableness is appropriate and otherwise consistent with the federal cost principles at 2 C.F.R. part. 225.
Based upon the information provided by the Applicant and FEMA’s independent analysis, FEMA has concluded that the additional $213,570.86 for the change order (the $237,244.86 change order amount less the $23,674.00 awarded in the first appeal decision) and additional $3,397.10 for the manhole are eligible for reimbursement. The Applicant also has provided documentation, in the form of vendor invoices, supporting its claim for an additional $2,359.85 for curb and gutter repair and replacement work, and FEMA is also approving the additional costs for such work. Furthermore, FEMA is not taking enforcement action based upon the Applicant’s noncompliance with the procurement standard at 44 C.F.R. § 13.43 by reducing these otherwise eligible costs.
The Applicant also seeks an additional $5,666.05 in DAC ($5,784.46 representing actual costs, less $94.73 awarded in PW 2432 and $23.68 awarded in PW 2425). In support of this request, the Applicant provided a list of six staff members it asserts engaged in administrative activities pertaining to PW 2432. This documentation consists of a listing of hours worked, brief descriptions of the work, and timesheets establishing that the work was actually performed. The additional DAC is approved, pending final cost reconciliation at closeout.
The requested costs for lift station and asphalt repairs are not germane to this appeal, however, as that work was not included in the scope of work for PW 2432, the only PW at issue in this appeal. The Applicant must submit a separate appeal or appeals in order to seek reimbursement for claimed costs not associated with PW 2432. As such, FEMA is denying the requests for additional costs for the lift station and asphalt repairs.
Conclusion
The damage to the three sewer lines and manhole was caused by the disaster event, and the work as described in the change order was necessary to accomplish the needed repairs. The Applicant complied with the method of procurement requirements under 44 C.F.R. § 13.36(d) for both the original procurement and the change order, but failed to comply with the cost analysis requirement for the change order required by 44 C.F.R. § 13.36(f). Notwithstanding this noncompliance, FEMA will exercise its discretion to not take enforcement action by reducing otherwise eligible costs incurred by the Applicant for eligible work. FEMA will, therefore, increase the amount awarded under PW 2432 by an additional $213,570.86 for costs incurred under the change order, $3,397.10 for the manhole, $2,359.85 for curb and gutter repair and replacement, and $5,666.05 for DAC. However, FEMA is denying the requests for additional costs for the lift station and asphalt repairs.
[1] PW 2432 did not capture the costs for which the Applicant was responsible; those costs were addressed in a separate PW, PW 2425.
[2] Under FEMA’s calculation, the additional requested amount should be $249,067.82 (the Applicant’s asserted total project costs of $370,612.96, less the original $90,775.33 obligated in PW 2432, the $23,674.00 in additional costs awarded by the Regional Administrator, and $7,095.81 for asphalt repairs associated with the site captured in PW 2425).
[3] Robert T. Stafford Disaster Relief and Emergency Assistance Act, Pub. L. No. 93-288, § 406 (1974) (codified as amended at 42 U.S.C. § 5172) [Stafford Act].
[4] Id. (Permanent work authorized by Section 406 of the Stafford Act must be for a facility “damaged or destroyed by a major disaster”); 44 C.F.R. § 206.223(a)(1).
[5] 44 C.F.R. § 13.22.
[6] 44 C.F.R. § 13.36(c).
[7] See Federal Emergency Management Agency, Procurement Disaster Assistance Team, Field Manual – Public Assistance Grantee and Subgrantee Procurement Requirements Under 44 C.F.R. pt. 13 and 2 C.F.R. pt. 215, at 11 (Dec. 2014) [“FEMA PDAT Field Manual”]. See also 48 C.F.R. § 2.101, which defines “full and open competition” with respect to federal acquisitions (“Full and open competition, when used with respect to a contract action, means that all responsible sources are permitted to compete.”).
[8] 44 C.F.R. § 13.36(d)(1)-(3).
[9] 44 C.F.R. § 13.36(d)(1). On August 30, 2010, the Civilian Agency Acquisition Council published an updated simplified acquisition threshold of $150,000 in the Federal Register. 75 Fed. Reg. 53,129 (Aug. 30, 2010). See 41 U.S.C. § 1908; 48 C.F.R. Subpart 2.1 (Definitions).
[10] 44 C.F.R. § 13.36(d)(1).
[11] 44 C.F.R. § 13.36(d)(2). This regulation sets forth the various procedural requirements that a local government must meet in using the sealed bid method at 44 C.F.R. § 13.36(d)(2)(ii).
[12] 44 C.F.R. § 13.36(d)(2)(i).
[13] 44 C.F.R. § 13.36(d)(3).
[14] Id. The regulation sets forth the various procedural requirements that a local government must meet in using the competitive proposal method at 44 C.F.R. § 13.36(d)(3)(i)-(v).
[15] 44 C.F.R. § 13.36(d)(4).
[16] 44 C.F.R. § 13.36(d)(4)(ii).
[17] Id.
[18] Id.
[19] See FEMA PDAT Field Manual, pp. 38-39.
[20] See id.
[21] See 44 C.F.R. § 13.36(d)(2)(ii)(A) (“(A) The invitation for bids will be publicly advertised and bids shall be solicited from an adequate number of known suppliers, providing them sufficient time prior to the date set for the opening of bids.”) (emphasis added).
[22] We note that the Applicant relied upon an emergency procurement authority under state law in conducting its original procurement. S.D. Codified Laws § 5-18A-9. This law provides that “A purchasing agent may make or authorize others to make an emergency procurement without advertising the procurement if rentals are not practicable and there exists a threat to public health, welfare, or safety or for other urgent and compelling reasons.” An emergency procurement “shall be made with such competition as is practicable under the circumstances.” However, even though the Applicant’s original procurement may have complied with state and local law, it must also meet the minimum requirements of the regulation at 44 C.F.R. § 13.36.
[23] The use of small purchase procedures is not required and, if a local government does use this method, it must be consistent with the local government’s procurement procedures which reflect applicable state and local laws and regulations. FEMA has accepted the Applicant’s assertion that the procurement method for the original contract complied with its procurement procedures, such that the only issue addressed in this appeal is whether the method of procurement complied with the federal regulation.
[24] 44 C.F.R. § 13.36(d)(1).
[25] FEMA Recovery Fact Sheet No. 9580.212, Public Assistance Frequently Asked Questions, ¶ 3 (Oct. 28, 2012).
[26] See U.S. Environmental Protection Agency, Source Water Protection Practices Bulletin – Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water (Jul. 2001) (“SSOs and CSOs can carry bacteria, viruses, protozoa, helminths (intestinal worms), and inhaled molds and fungi directly into source water, and can cause diseases that range in severity from mild gastroenteritis to life-threatening ailments such as cholera, dysentery, infectious hepatitis, and severe gastroenteritis. People can be exposed to the contaminant from sewage in drinking water sources, and through direct contact in areas of high public access such as basements, lawns or streets, or water used for recreation.”).
[27] See FEMA PDAT Field Manual, pp. 38-39.
[28] See id. The broader standards applied in Federal contracting practice reflected in Federal court decisions, Federal Boards of Contract Appeals decisions, and Comptroller General decisions provide useful guidance in determining whether a change would be treated as a cardinal change. FEMA does not imply that these Federal procurement decisions are controlling, but FEMA considers the collective wisdom within these decisions in determining the nature of third party contract changes along the broad spectrum between permissible and impermissible changes. For a general overview of the tests used to analyze the permissibility of changes in federal contracts, see John Cibinic, Jr. and Ralph C. Nash, Administration of Government Contracts, 379-, 391, 4th Ed. Chicago: CCH Incorporated, 2006.
[29] “Infeasible.” Merriam-Webster.com. Accessed June 17, 2014. //www.merriam-webster.com/dictionary/infeasible (defining “infeasible” as “not feasible; impracticable”). The term “impracticable” means something that is not capable of being done, effected, or accomplished. “Impracticable.” Merriam-Webster.com. Accessed June 17, 2014. //www.merriam-webster.com/dictionary/impracticable (defining “impracticable” as “incapable of being performed or accomplished by the means employed or at command”).
[30] S.D. Codified Laws § 5-18A-14.
[31] “Exigent.” Merriam-Webster.com. Accessed June 17, 2014. //www.merriam-webster.com/dictionary/exigent. (defining “exigent” as “(1) requiring immediate aid or action <exigent circumstances>; (2) requiring or calling for much; demanding <an exigent client>”).
[32] “Emergency.” Merriam-Webster.com. Accessed June 17, 2014. //www.merriam-webster.com/dictionary/emergency. (defining “emergency” as “(1) an unforeseen combination of circumstances or the resulting state that calls for immediate action; (2) an urgent need for assistance or relief <the mayor declared a state of emergency after the flood>”).
[33] FEMA PDAT Field Manual, p. 68.
[34] Id.
[35] 44 C.F.R. § 13.36(d)(4)(ii).
[36] Public Assistance Guide, FEMA 322 (June 2007), at 41.
[37] To independently evaluate these costs, FEMA did a search for all sewer projects for the City of Pierre, and calculated the average cost per day of the awarded contracts only. The average cost in five awarded contracts was $5,637/day, with a range of $4,095/day to $9,167/day. The contracted cost of the change order pertaining to this PW was $5,649/day, similar to the average.